Loading...
HomeMy WebLinkAbout091790Minutes Special Board Meeting September 17, 1990 Present: Lars, Mike, Gwen, Bev, Sue Roof project- - We received 3 bids with FS S GS from Tacoma being the lowest. MSP to award the contract to FS s GS There was some discussion about the budget for this project and the need to let the City Council know that in there will be costs beyond the bid amount, i.e. Bob's fee, sales tax, permits, etc. The project will still come in under the $30,000 first estimated. Landscape Committee— The landscape committee has hired John Barr and will begin working with him on design development. Mike presented design criteria. The project budget is $10,000 from which we want to end up with a completed project. Bev Shelton 0 L. J