Project
Bell Tower-Emergency Repairs 9'' gc,`A, o
Port Townsend,Washington
To Contractor Change Order Number: 05
Hoch Construction,Inc. Date: 05-29-12
4201 Tumwater Truck Route City Project No.: W.O.2012
Port Angeles,WA 98363 Contract Date: 01-10-2012
Contract For: Bell Tower Support Leg Replacement
The Contract is Changed as Follows:
The Contract Sum is changed per the review Change Order Proposals (COP) submitted by the Contractor and summarized
below:
COP-12 $ 5,263.20 Equipment rental:03/08/2012-04/07/2012
COP-13 $ 2,105.28 Equipment rental:04/08/2012-04/19/2012
COP-14 $ 317.86 SaniCan Rental 02/05/2012-05/14/2012
Sales Tax $ 691.78
Total for this Change Order $ $,378.12
The Original Contract Sum $ 109,976.11
The Net Change by Previous Change Orders $ 33,301.30
The Contract Sum prior to this Change Order $ 146,274.53
The Contract Sum will be increased by this Change Order amount of: $ 8,378.12
The New Contract Sum including this Change Order will be: $ 154,652.65
The Contract Time will be changed by: 0 days.
The date of Substantial Completion as of the date of this Change Order therefore is: May 29,2012
NOT VALID UNTIL SIGNED BY CONTRACTOR AND OWNER.
Contractor Owner
Hoch Construction, Inc. City of Port Townsend
4021 Tumwater Truck Route 250 Madison°Str eet,Suite 2
2ngp�MA Port 9 63 Port Town 983684'
BY: BY: David Timmons`
Date J Date
Page 1 of 1 CO-5 BT