RESOLUTION NO.26-015
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF PORT TOWNSEND,
WASHINGTON, AUTHORIZING THE APPLICATION FOR LOAN FUNDING FOR
REMAINING DESIGN AND CONSTRUCTION OF THE HOLCOMB AND WILSON
STREET SEWER UPSIZING PROJECT IN AN AMOUNT NOT TO EXCEED
$2,169,000
WHEREAS, the City of Port Townsend's ("City") 2024 Adopted General Sewer Plan
identifies Capital Improvement Plan Project No. SM1, SM3, and SM6 to replace and upsize
gravity sewer infrastructure near Holcomb and Wilson streets to address hydraulic capacity
deficiencies and projected peak flows; and
WHEREAS, the Holcomb and Wilson Sewer Upsizing Project will replace and relocate
approximately 2,410 linear feet of existing gravity sewer using a new 12-inch and 18-inch gravity
sewer alignment, improve long-term maintenance access, and provide the downstream capacity
needed for projected flows from the Rainier Subarea and future Mill Road Lift Station; and
WHEREAS, the City will apply for a loan from the Washington State Public Works Board
to finance eligible remaining design and construction costs in an amount not to exceed
$2,169,000; and
WHEREAS, the City commits to providing required local matching funds, repaying the
loan, and abiding by the provisions of the loan agreement, if awarded;
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Port
Townsend to authorize application to the Washington State Public Works Board for loan
financing for remaining design and construction of the Holcomb and Wilson Street Sewer
Upsizing Project in an amount not to exceed $2,169,000.
ADOPTED by the City Council of the City of Port Townsend at a regular meeting thereof,
held this 20th day of July, 2026.