HomeMy WebLinkAboutJefferson Healthcare Hospital - Geotech Report 2023rlrtrI
RILEYGR(]UP
UPDATED GEOTECHNICAL ENGINEERING REPORT
Pnrpeneo Bv:
Txe RruY Gnoue, lruc.
L7522 Bornru- Wav NonrHEAsr
Bornrrr, WRsttrneroru 98011
PnepRnro ron:
Jerrensoru HrRrrxcRne
834 SnrmoRru Stneer
Ponr Towruseru o, WRsxttucroru 98358
RGf Pnorecr No. 2022-387-t
JerreRsoru HERlrncRRe Sourn Clrupus RepncrueNT AND Aoortoru
834 SxentoRru Srneer
Ponr Townsrruo, WRsttIuetoru
hruunnv t2,2O23
Coryorote Olfice
77522 Bothell Way Northedst
Bothell, Woshington 98017
Phone 425.475.0551 a Fax 425.475.0311
www.riley-group.com
TIIlr!
RILEVGR()UP
January L2,2023
Aaron Vallat
Jefferson Healthcare
834 Sheridan Street
Port Townsend, Washington 98368
Subject: Geotechnical Engineering Report
Jefferson Healthcare South Campus Replacement and Addition
834 Sheridan Street
Port Townsend, Washington
Project No.2022-387-t
Dear Aaron Vallat:
As requested, The Riley Group, lnc. {RGl) has performed a Geotechnical Engineering Report
(GER) for the Jefferson Healthcare South Campus Replacement and Addition project
located at 834 Sheridan Street, Port Townsend, Washington. Our services for updating the
previous report were completed in accordance with our proposal dated November 2,2022
and authorized by Mike Glenn on November L3, 2022. The information in this GER is based
on our understanding of the proposed construction, and the soil and groundwater
conditions encountered in the borings completed by RGI at the site on August 30 and 31-,
2022 and the test pits and infiltration tests completed on January 4,2A23.
RGI recommends that you submit the project plans and specifications for a general review
so that we may confirm that the recommendations in this GER are interpreted and
implemented properly in the construction documents. RGI also recommend that a
representative from ourfirm be present on site during portions of the project construction
to confirm that the soil and groundwater conditions are consistent with those that form
the basis for the engineering recommendations in this GER.
lf you have any questions or require additional information, please contact us.
Respectfu lly su bm itted,
Tnr RneY GRoue, lruc.
lof zotz
lrclzoz)
Eric L. Woods, LG
Project Geologist
Kristina M, Weller, PE
Principal Geotechnical Engineer
Corporate Ollice
77522 Bothell Woy Northeast
Bothell, Woshington 98077
Phone 425.475.0557 | Fox 425.475,0377
www,riley-group,com
ERIC L. WOODS
M Rta
a
Geotech nical Eng i nee ring Re port
JeJferson Heolthcdre South Campus, Port Townsend, Washington
Jonuory 72,2023
RGI Project No. 2022-387-7
Taele oF CoNTENTS
1.0
2.0
3.0
INTRODUCTION..........
PROJECT DESCRIPTION .............
FIELD EXPLORATION AND LABORATORY TESTING.................
3,1 Frelo ExPLoRAToN .....
3,2 LABoRAToRY TESTING ,.
1
I
1
L
2
4.0 SITE CONDITIONS......
4.1 SURFACE,
4.2 GEoLoGY
4.3 Sot1s...........
4.4 GRouNDWATER .............
4.5 SEtsMrc coNstDERAT|oNs ...........,..,.........
4.6 GEoLoGIc HAZARD AREAS
5.2.1 SoilConditions.
5.2.2 Groundwater Conditions....
5.2.3 Soil NailWalls..
5.2.4 Soldier Pile and Tieback Shoring ..........
5.2,5 1agginC.,.,,,.,,.........
5.2.5 Tiebacks.................
2
2
2
2
3
3
4
5.0 DISCUSSIONANDRECOMMENDATIONS 4
5.1 GEoTEcHNICAL CoNSIDERATIONS 4
5.1,1 Erosion and Sediment Control
.....5
5.2 SHoRING RECoMMENDATIONS,
.,............'..'.,........ 4
.........................,.. 5
'..,.'....'..'..6
6
6
''.'''''.'.',,.'.'.'''''7
o
........10
8
11
L2
L2
L2
13
L4
L4
15
15
16
15
16
L7
L7
17
17
18
19
19
20
5.2,7 Construction Monitoring.................,....
5.3 EARTHWoRK..
5.3.1 Site Preparation
5.3.2 Structural Fi11...........
5.3.3 Wet Weather Construction Considerations....
5.4 FouruonroNs,.,..,........
5.4.1 Shallow foundations.........
5,5 RETAINING WALLS
5.5.1 Permanent Basement Wa1|s..................
5.5.2 Retaining Wall Design
5,6 SLAB-oN-GRlor CorusmucloN ......,...
5,7 DRAINAGE
5.7.1 Surface...........,.,
5.7.2 Subsurface
5.7.3 lnfiltration
5.8 UTILITIES.
5.9 PAVEMENTS.....
ADDITIONAL SERVICES.........,......
5.2.8 Survey Monitoring... '.'."".'L2
tlIlrI
RILEYGR(lUP
6.0
7.0
Geotechnical Engineering Repon
Jefferson Healthcare South Compus, Port Townsend, Wdshington
Jonuary 72,2O23
RGI Project No. 2022-387-7
Lsr or FteuRes AND APPENDtcEs
Figure 1 .........
Figure 2.........
Figure 3 .........
Figure 4.........
Figure 5 .........
Figure 6.........
Figure 7 .........
Figure 8 .........
Figure 9 .........
Appendix A....
.............. Vicinity Map
.... Geotechnical Exploration Plan
Soldier Pile Pressure Diagram
................ Earth Pressure - Single Tieback
............ Earth Pressure - M ultiple Tieback
... Surcharge Load
................ Basement Wall Drainage Detail
................. Retaining Wall Drainage Detail
...Typical Footing Drain Detail
.Field Exploration and Laboratory Testing
ItIlrI
RILEYGR(}UP
Geotechnico I Eng i nee ring Re port
lefferson Hedlthcore South Campus, Port Townsend, Washington
Janudry 72,2023
RGI Project No. 2022-387-7
Executive Summary
This Executive Summary should be used in conjunction with the entire Geotechnical
Engineering Report (GER)for design and/or construction purposes. lt should be recognized
that specific details were not included or fully developed in this section, and the GER must
be read in its entirety for a comprehensive understanding of the items contained herein.
Section 7.0 should be read for an understanding of limitations.
RGI's geotechnical scope of work included the advancement of ten borings to approximate
depths of 10.5 to 21.5 feet below existing site grades. An additional 2 infiltration test pits
were conducted January 4,2023 to the depths of 4.5 to 6 feet below existing grade.
Based on the information obtained from our subsurface exploration, the site is suitable for
development of the proposed project. The following geotechnical considerations were
identified:
Soil Conditions: The soils encountered during field exploration include up to 8 feet of fill
comprised of loose to dense silty sand with trace gravel over loose to dense surficial
deposits comprised of silty sand with trace gravel over medium dense to very dense silty
sand with trace gravel glacialtill.
Groundwater: Groundwater seepage was encountered at Boring B-1 at a depth of 21 feet
during our subsurface exploration.
Foundations: Foundations for the proposed building may be supported on conventional
spread footings bearing on medium dense to dense native soil or structural fill. Micropiles
will be used for some foundations adjacent to a retaining wall.
Slab-on-grade: Slab-on-grade floors and slabs for the proposed building can be supported
on medium dense to dense native soil or structural fill.
Pavements: The following pavement sections are recommended:
crushed rock base (CRB)
ItItrI
RILEYGR()UP
Geotechnical Engineering Report Page 1
lefferson Healthcare South Campus, Port Townsend, Washington
January L2,2023
RGI Project No. 2022-387-1
1.0 lntroduction
This Geotechnical Engineering Report (GER) presents the results of the geotechnical
engineering services provided for the Jefferson Healthcare South Campus Replacement and
Addition project in Port Townsend, Washington. The purpose of this evaluation is to assess
subsurface conditions and provide geotechnical recommendations for the expansion of the
existing building and addition of parking and drive areas. Our scope of services included
field explorations, laboratory testing, engineering analyses, and preparation of this GER.
The recommendations in the following sections of this GER are based upon our current
understanding of the proposed site development as outlined below. lf actual features vary
or changes are made, RGI should review them in order to modify our recommendations as
required. ln addition, RGI requests to review the site grading plan, final design drawings
and specifications when available to verify that our project understanding is correct and
that our recommendations have been properly interpreted and incorporated into the
project design and construction.
2.O Projectdescription
The project site is located at 834 Sheridan Street in Port Townsend, Washington. The
approximate location of the site is shown on Figure 1.
The site is currently occupied by the Jefferson Healthcare South Campus building and
associated parking and drive areas, and a storm drainage pond. RGI understands that a one-
story portion of the existing building will be replaced and expanded, and will include a
daylight basement level on a portion of the building. The expansion will include additional
parking in the eastern and southern portions of the property. Future development plans
include a 3-story addition to the south of the existing structures.
3.0 Field Exploration and Laboratory Testing
3.1 Ftrt-o Expr-oRATtoN
RGI observed the drilling of 10 borings on August 30th and 31't. Additionally RGI observed
the excavation of 2 infiltration test pits on January 4,2023. The'approximate exploration
locations are shown on Figure 2.
Field logs of each exploration were prepared by the geologist that continuously observed
the drilling. These logs included visual classifications of the materials encountered during
drilling as well as our interpretation of the subsurface conditions between samples. The
boring logs included in Appendix A represent an interpretation of the field logs and include
modifications based on laboratory observation and analysis of the samples.
ItIlrI
RILEYGR()UP
Geotechnical Engineering Reporr Page2
lefferson Healthcare South Campus, Port Townsend, Washington
Januarv t2,2O23
RGI Project No. 2022-387-1
3.2 LeeoRRroRY TESnNG
During the field exploration, a representative portion of each recovered sample was sealed
in containers and transported to our laboratory for further visual and laboratory
examination. Selected samples retrieved from the borings were tested for moisture
content and grain size analysis to aid in soil classification and provide input for the
recommendations provided in this GER. The results and descriptions of the laboratorytests
are enclosed in Appendix A.
'4.0 Site Conditions
4.L Sunrnce
The subject site is bound to the west by Sheridan Street, to the north by 9th Street, Hospital
Road, and a single-family residence, to the east by Gise Street, and to the south by 7th
Street. One proposed parking area to the south is bound to the north by 7th Street, to the
east by single family-residences, to the south by 6th Street, and to the west by Cleveland
Street, and the other parking area to the south is bound to the west by Sheridan Street, to
the north by a commercial development, to the east by Cleveland Street, and to the south
by an undeveloped alignment of 5th Street.
The site is occupied by the Jefferson Healthcare South Campus and associated paved and
gravel parking areas. The site slopes generally east with an elevation change of
approximately 60 feet. The site is vegetated primarily with grass and decorative plants and
shrubs.
4.2 Geoloev
Review of the Geologic Map of the Port Townsend South ond Part of the Port Townsend
North 7.S-minute Quadrangles, Jefferson County, Woshington, by Henry W. Schasse, etc.
(2005) indicates that much of the site is mapped as Modified land (Map Unit Qml), which
is soils reworked by developments. The southern portion of the site is mapped as
Lodgement till (Qgt), which is a compact mixture of clay, silt, sand, and gravel, deposited
by glacial ice. These descriptions are generally similar to the findings in our field
explorations.
4.3 Sorls
The soils encountered during field exploration include up to 8 feet of fill comprised of loose
to dense silty sand with trace gravel over loose to dense surficial deposits comprised of silty
sand with trace gravel over medium dense to very dense silty sand with trace gravel (glacial
till).
ItIlrI
RILEYGR(}UP
Geotechnical Engineering Report Page 3
Jefferson Healthcare South Campus, Port Townsend, Washington
January !2,2023
RGI Project No. 2022-387-1
More detailed descriptions of the subsurface conditions encountered are presented in the
boring logs included in Appendix A. Sieve analysis was performed on two selected soil
samples. Grain size distribution curves are included in Appendix A.
4.4 GRourrrowRrrn
Groundwater seepage was encountered at Boring B-1 at a depth of 21 feet during our
subsurface exploration. A groundwater monitoring well was installed in Boring B-1 and B-
4 to allow winter groundwater level readings. No water was observed in the well locations
on January 4,2023.
It should be recognized that fluctuations of the groundwater table will occur due to
seasonal variations in the amount of rainfall, runoff, and other factors not evident at the
time the explorations were performed. ln addition, perched water can develop within
seams and layers contained in fill soils or higher permeability soils overlying less permeable
soils following periods of heavy or prolonged precipitation. Therefore, groundwater levels
during construction or at other times in the future may be higher or lower than the levels
indicated on the logs.
4.5 Sersvuc CorusroeRRrrorus
Based on the 2018 lnternational Building Code (lBC), RGI recommends the follow seismic
parameters for design.
Table 12018 IBC
Parameter Value
Site Soil Classl gz
Site Latitude 48.1061
Site Longitude -r22.789r
Short Period Spectral Response Acceleration, Ss (g)1.335
1-Second Period Spectral Response Acceleration, Sr (g)o.487
Adjusted Short Period Spectral Response Acceleration, Srvs (g)1.335
Adjusted l-Second Period Spectral Response Acceleration, Srvr (g)0.8843
Numeric seismic design value at 0.2 second; Sos(g)0.89
Numeric seismic design value at 1.0 second; Sor(g)0.5893
1. Note: I n general accordance with Chapter 20 of ASCE 7-16. The Site Class is based on the average characteristics of the upper 100 feet
of the subsurface profile.
2. Note: ASCE 7-16 require a site soil profile determination extending to a depth of 100 feet for seismic site classification. The current
scope of our services does not include the required 100 foot soil profile determination. Borings extended to a maximum depth of 21.5
feet, and this seismic site class definition considers that very dense soil continues below the maximum depth of the subsurface
ttIlrI
RILEYGR()UP
Geotechnical Engineering Report Page4
Jefferson Healthcare South Campus, Port Townsend, Washington
January 12, 2023
RGI Project No. 2022-387-1
exploration. Additional exploration to deeper depths would be required to confirm the conditions below the current depth of
exploration.
Liquefaction is a phenomenon where there is a reduction or complete loss of soil strength
due to an increase in water pressure induced by vibrations from a seismic event.
Liquefaction mainly affects geologically recent deposits of fine-grained sands that are
below the groundwater table. Soils of this nature derive their strength from intergranular
friction. The generated water pressure or pore pressure essentially separates the soil grains
and eliminates this intergranular friction, thus reducing or eliminating the soil's strength.
RGI reviewed the results of the field and laboratory testing and assessed the potential for
liquefaction of the site's soil during an earthquake. Since the site is underlain by glacial till
and glacially consolidated deposits, RGI considers that the possibility of liquefaction during
an earthquake as minimal.
4.6 Groloe rc Hazeno Aneas
Regulated geologically hazardous areas include erosion, landslide, earthquake, or other
geological hazards. Based on the definitions in the Port Townsend Municipal Code, the site
does not contain geologically hazardous areas.
5.0 DiscussionandRecommendations
5.1 GeorrcnucAtCoNstDERATIoNs
Based on our study, the site is suitable for the proposed construction from a geotechnical
standpoint. Foundations for the proposed building can be supported on conventional
spread footings bearing on medium dense to very dense native soil or structural fill. Slab-
on-grade and pavements can be similarly supported.
Detailed recommendations regarding the above issues and other geotechhical design
considerations are provided in the following sections. These recommendations should be
incorporated into the final design drawings and construction specifications.
5.1.1 Enosrorrr nruo SeotrurNT CoNTRoL
Potential sources or causes of erosion and sedimentation depend on construction
methods, slope length and gradient, amount of soil exposed and/or disturbed, soil type,
construction sequencing and weather. The impacts on erosion-prone areas can be reduced
by implementing an erosion and sedimentation control plan. The plan should be designed
in accordance with applicable city and/or county standards.
RGI recommends the following erosion control Best Management Practices (BMPs):
and undertaking activities that expose soil during periods of little or no rainfall
llIlrI
RILEYGR(}UP
Geotechnical Engineering Report Page 5
Jefferson Healthcare South Campus, Port Townsend, Washington
Januarv t2,2023
RGI Project No. 2022-387-1
side of work areas
if surfaces will be left undisturbed for more than one day during wet weather or
one week in dry weather
excavation surfaces with anchored plastic sheeting (Graded and disturbed slopes
should be tracked in place with the equipment running perpendicular to the slope
contours so that the track marks provide a texture to help resist erosion and
channeling. Some sloughing and raveling of slopes with exposed or disturbed soil
should be expected.)
contractor should be aware that inspection and maintenance of erosion control
BMPs is critical toward their satisfactory performance. Repair and/or replacement
of dysfunctional erosion control elements should be anticipated.)
Permanent erosion protection should be provided by reestablishing vegetation using
hydroseeding and/or landscape planting. Until the permanent erosion protection is
established, site monitoring should be performed by qualified personnel to evaluate the
effectiveness of the erosion control measures. Provisions for modifications to the erosion
control system based on monitoring observations should be included in the erosion and
sedimentation control plan.
5.I.2 SrRtpplrrrc
Stripping efforts should include removal of pavements, vegetation, organic materials, and
deleterious debris from areas slated for building, pavement, and utility construction.
Deeper areas of stripping may be required in forested or heavily vegetated areas of the
site.
5.1.3 Excevarrons
All temporary cut slopes associated with the site and utility excavations should be
adequately inclined to prevent sloughing and collapse. The site soils consist of medium
dense to very dense silty sand with trace gravel.
Accordingly, for excavations more than 4 feet but less than 20 feet in depth, the temporary
side slopes should be laid back with a minimum slope inclination of 1H:1V
(Horizontal:Vertical). lf there is insufficient room to complete the excavations in this
manner, or excavations greater than 20 feet in depth are planned, using temporary shoring
!lIIrr
RILEYGR(1UP
Geotechnical Engineering Report Page 6
Jefferson Healthcare South Campus, Port Townsend, Washington
January 12,2023
RGI Project No. 2022-387-1
to support the excavations should be considered. Shoring recommendations are provided
in the following section of this GER.
For open cuts at the site, RGI recommends:
the top of cut slopes within a distance of at least 5 feet from the top of the cut
tarps and/or plastic sheeting
is left open is minimized
engineer to confirm adequate stability and erosion control measures
ln all cases, however, appropriate inclinations will depend on the actual soil and
groundwater conditions encountered during earthwork. Ultimately, the site contractor
must be responsible for maintaining safe excavation slopes that comply with applicable
OSHA or WISHA guidelines.
5.2 SxontrucRrcorunneruDATtoNs
RGI anticipates that an excavation ranging up to about 20 feet deep will be needed at the
site to accommodate the proposed building and substructure. Our geotechnical comments
and recommendations concerning site excavations are presented below.
5.2.1 Son Coruomorus
Based on our explorations, RGI anticipates that the on-site excavation will encounter
primarily silty sand with trace gravel. These soils can be readily excavated with
conventional earthworking equipment, in our estimation, but extra effort will be needed
in the glacial till soils. Although our explorations did not reveal rubble within the fill soils or
boulders within the native soils, such obstacles could be present at random locations within
these deposits.
5.2.2 GRounownreR Coruomorus
Our explorations encountered groundwater at depths of about 21feet below grade at the
time of drilling, but we expect that groundwater levels will rise several feet during the late
winter and spring months. A groundwater monitoring well was installed and winter
monitoring should be completed to determine if the groundwater will impact the proposed
basement level or shoring installation.
ttIlrI
RILEYGR{)UP
Geotechnical Engineering Report PageT
Jefferson Healthcare South Campus, Port Townsend, Washington
Unit Weight
tpcfl
Januarv L2,2O23
RGI Project No. 2022-387-1
5.2.3 Son NnllWalls
Based on our experience with similar soils, we expect soil nails and shotcrete will be feasible
for shoring during excavation. The first row of soil nails need to be carefully installed if
utilities are present in the area. Vertical nail elements may be needed for additional lateral
support.
Soil nailing stabilizes vertical excavations by reinforcing the soil mass with passive
inclusions (soil nails). Soil nails typically consist of 3/a- to 1-3/8-inch-diameter steel bars
that are centrally grouted in 6- to 8-inch-diameter augered holes. The nails are normally
spaced at 4 to 6-foot centers. Following the installation of a row of nails, the excavation
face is covered with a shotcrete facing that is reinforced with either welded wire mesh or
rebar. The nails are then secured to the shotcrete wall with a steel plate and bolt assembly.
Once grout strengths are achieved, the excavation continues below the wall and the
construction sequence is repeated untilthe bottom of the excavation is reached.
Soil Nail Design
Based on the soils encountered at the site, RGI recommends using the following soil
parameters for soil nailing design:
Table 2 Soil Nail Design Parameters
SoilParameter Cohesion Shaft
Resistance
(psf)
Dense to very dense 1,500stsand
Excavation and wall construction sequencing should not exceed a height of 6 feet. Care
must be taken to prevent caving during initial excavation in loose fill. Temporary protection
such as soil berms and flash coating should be considered. The shaft resistance assumes
open hole tremie grouting. Soil nail verification tests should be performed to verify the soil
resistance before construction.
Conflicts and Easements
Because soil nails typically extend about 30 to 40 feet behind the excavation face, conflicts
with underground utilities and adjacent structures often arise. The project structural
engineer or shoring designer should carefully consider the locations of such obstructions
when laying out all tiebacks. Furthermore, temporary easements will be required for any
nails that extend beyond the site's property boundaries, and it should be realized that the
City does not typically allow permanent tiebacks under their roadways and alleyways.
Friction
Angle (psfl
rlIlrI
RILEYGR(1UP
L25 38 100
Geotechnical Engineering Report Page 8
Jefferson Healthcare South Campus, Port Townsend, Washington
)anuary L2,2Q23
RGI Project No. 2022-387-1
5.2.4 Soloren Ptt aruo Ttrencr Snontruc
ln our opinion, soldier piles can be used in either a cantilevered or a tied-back configuration
for shoring the proposed excavation sidewalls at the site. The following geotechnical
comments and recommendations are provided concerning soldier piles'
Soldier Pile Embedment
All soldier piles must have sufficient embedment below the final excavation levelto provide
adequate kick-out resistance to horizontal loads, as calculated by the design engineer. RGI
recommends providing a minimum embedment of 10 feet below the excavation base
directly in front of each pile. For cantilevered soldier piles, RGI further recommends that
the embedment depth not be less than the exposed wall height.
Drilling Conditions
Our subsurface explorations revealed that the site is underlain by layers of loose to very
dense sands and stiff to hard silts. These soils can likely be drilled with a conventional auger,
but the very dense and hard layers will undoubtedly yield slow drilling rates. Although
none of our explorations encountered cobbles or boulders, it should be realized that such
obstructions could exist at random locations within these deposits. Groundwater seepage
should be expected at various depths throughout each borehole.
Applied Loads
All soldier piles at the subject site should be designed to resist the various lateral loads
applied to them. For a temporary shoring wall, RGI expects that these lateral loads will
consist of active or at-rest pressures and possibly traffic surcharge or structural surcharge
pressures, depending on the specific wall location. For a shoring wall that has adequate
drainage, RGI does not expect that hydrostatic pressures will need to be considered. Our
recommended design pressures are presented graphically on Figures 3 through 5 and are
discussed in the following paragraphs.
row of tiebacks can be designed using active earth pressures modeled as the
equivalent fluid densities shown on Figures 3 and 4. Tied-back walls that have two
or more rows of tiebacks should be designed using the trapezoidal pressure
distribution shown on Figure 5. From the backslope level to the foreslope level,
these active pressures should be applied over the soldier pile spacing; below the
foreslope level, the pressures need be applied over just one pile diameter.
should be increased to account for any structural loads located within a horizontal
. distance equal to half the wall height. lf existing footings or other structural loads
are found to exist within this distance, RGI should be contacted to calculate the
appropriate surcharge pressures.
ttrlrI
RILEYGR(}UP
Geotechnical Engineering Report Page 9
Jefferson Healthcare South Campus, Port Townsend, Washington
January 12,2023
RGI Proiect No. 2022-387-1
should be increased to account for traffic, construction equipment, material
stockpiles, or other temporary loads located within a horizontal distance equal to
half the wall height. For light to moderately heavy vehicles, this traffic surcharge
can be modeled as a uniform lateral pressure of 75 psf acting overthe upper 8 feet
of wall; or heavy vehicles, such as concrete trucks, a value of 150 psf would be more
appropriate.
a net hydrostatic pressure of 45 pcf would act against the portion of wall above the
foreslope level and below the saturation level. However, if adequate drainage is
provided behind the shoring wall, we expect that hydrostatic pressures will not
develop.
passive earth pressure acting over the embedded portion of each soldier pile,
neglecting the upper 2 feet. This passive pressure should be applied over a lateral
distance equal to the pile spacing or twice the pile diameter, whichever is less. For
a level foreslope (measured perpendicular to the wall face), RGI recommends using
a maximum allowable passive pressure modeled as an equivalent fluid density of
400 pounds per cubic foot (pcf).
tieback and underpinning may be calculated using an allowable end bearing of 15
kips per square foot (ksf) and an allowable friction of 1.5 ksf in the very denbe till
soils expected at the base of the piles.
horizontal modulus of subgrade reaction, which generally increases with depth. As
a reasonable approximation, however, a uniform modulus of 250 kips per cubic foot
(kcf) or 145 pounds per cubic inch (pci) can be used.
5.2.5 Lnecrruc
RGI recommends that lagging be installed between all adjacent soldier piles to reduce the
potential for soil caving, backslope subsidence, and hazardous working conditions. Our
geotechnical comments and recommendations about lagging are presented below.
Lagging Materiols
ln our opinion, either conventional wooden timbers or reinforced shotcrete panels could
be utilized as lagging at the site, but the former would likely be much less expensive. For
permanent shoring wall applications, RGI typically recommends that all wooden timber
lagging be pressure-treated. However, because the on-site shoring wall serves only a
temporary function, pressure-treated wooden lagging is not necessary.
llrlrI
RILEYGR(lUP
Geotechnical Engineering Report Page 10
Jefferson Healthcare South Campus, Port Townsend, Washington
January 12,2023
RGI Project No. 2022-387-1
Laterdl Pressures
Due to soil arching effects, temporary lagging that spans 8 feet or less need be designed
for only 50 percent of the lateral earth pressure previously recommended for soldier pile
design. Permanent lagging, on the other hand, should be designed for 75 percent of this
same lateral earth pressure. ln both cases, these values assume that adequate drainage is
provided behind the lagging, as discussed below.
Lagging Bockfill
RGI recommends that any voids behind the lagging be backfilled with a material sufficiently
pervious to allow groundwater flow and prevent a build-up of hydrostatic pressure. For this
reason, permeable materials such as granular excavation spoils, clean sand, or pea gravel
are suitable as backfill material, whereas silty soils, cement grout, controlled-density fill, or
other less-permeable materials are not suitable.
Drainage System
RGI recommends that all lagging backfill material connect to a continuous horizontal drain
located in front of the wall. This can be accomplished either by extending gravel under the
lagging or by providing gaps between the lagging boards. lf concrete or shotcrete walls are
to be placed against wooden lagging, prefabricated vertical drainage strips (such as
MiraDRAlN 5000') should be attached to each lagging bay.
5.2.6 Treencxs
RGI anticipates that tieback anchors might be needed to support any soldier pile walls
having an exposed height greater than about 15 feet. Our tieback comments and
recommendations are summarized below.
Conflicts ond Easements
Because tiebacks typically extend about 30 to 60 feet behind the excavation face, conflicts
with underground utilities and adjacent structures often arise. The project structural
engineer should carefully consider the locations of such obstructions when laying out all
tiebacks.
lnstallotion Methods
All tiebacks should be installed in a manner that minimizes caving and associated ground
subsidence. Typically, this involves drilling with a full-length casing or continuous flight
auger, as well as pumping grout from the bottom of each tieback hole with a tremie. lf
desired, the shoring contractor can use secondary pressure-grouting techniques to reduce
auger diameters and develop greater adhesion values.
ItrlrI
RILEYGR()UP
Geotechnical Engineering Report page 11
Jefferson Healthcare South Campus, Port Townsend, Washington
January 72,2O23
RGI Project No. 2022-387-1
No-Load Zone
The anchor portion of all tiebacks must be located a sufficient distance behind the retained
excavation face in order to develop resistance within a stable soil mass. We specifically
recommend that the anchorage be obtained behind a "no-load zone" defined by a plane
set back from the wall face a horizontal distance equal to 25 percent of the wall height and
projected upward at a 60-degree angle from the excavation base level. This configuration
is shown on Figures 4 and 5.
Anchor Length ond Spocing
The anchor portion of all tiebacks must have sufficient embedment below the backslope
surface and behind the no-load zone to provide adequate pull-out resistance to lateral
loads, as calculated by the design engineer. RGI recommends providing a minimum anchor
depth of 10 feet and a minimum anchor length of 20 feet. To avoid interactions between
adjacent tiebacks, RGI further recommends that a clear spacing of at least 5 feet be
maintained along the anchor zones.
Estimated Adhesion
lf properly grouted, an allowable concrete/soil adhesion of 1,500 psf can be assumed for
the anchor portion of a tieback located within the dense to very dense till soils. Secondary
pressure-grouting techniques can often achieve adhesions two to three times greater than
these values. ln all cases, however, the aitual design values will depend on the installation
method and should be confirmed by load-testing all tiebacks in the field.
Load Testing and Lock-Off
Field testing of temporary tiebacks is necessary to confirm design assumptions, verify the
integrity of individual tiebacks, and provide information regarding their short-term creep
characteristics. Our recommended tests are described below. After testing, each tieback
should be lockedoff at 100 percent of its design load.
production tiebacks at the site. RGI specifically recommends testing at least one
tieback on each side of the excavation. The test load should equal 200 percent of
the design capacity and the 150 percent load should be held for at least 60 minutes.
site. The test load should equal 130 percent of the design capacity and be held for
at least 10 minutes.
5.2.7 CorusrnucnonMorumoRlrue
Because shoring requires specialized installation and earthwork techniques to maintain
stable conditions during and after construction, RGI strongly recommends that an RGI
representative be retained to continuously monitor all construction activities. This would
ttIlrI
RILEYGR()UP
I
Geotechnical Engineering Report Page 12
Jefferson Healthcare South Campus, Port Townsend, Washington
)anuary L2,2023
RGI Project No. 2022-387-1
include observation and documentation of installation procedures, construction materials,
drilling conditions, and load testing.
5.2.8 SuRvev MoruroRtrue
A monitoring program must be implemented to verify the performance of the shoring
system and possible excavation effects on neighboring buildings and existing alley. The first
step in this program should consist of surveying building feature elevations and
documenting the condition of the existing properties, alley and adjacent buildings. This
documentation should include a photographic record. Monitoring points should be set by
a licensed surveyor on the adjacent streets and structures at a maximum of 25 foot
intervals with a minimum of two on each side of the excavation.
Monitoring of the shoring system should occur two times per week as the excavation
proceeds and then once every two weeks once the excavation is completed. A registered
land surveyor should be retained to establish the baseline data and obtain the bi-weekly
readings. Monitoring data can be obtained by the project contractor. Monitoring should
continue until the permanent new lower walls are adequately braced and should include
surveying the vertical and horizontal alignment of the top of every other soldier pile or at
15 foot intervals on the soil nail wall. The project's structural and geotechnical engineers
should review the monitoring data weekly.
5.3 ElnrHwonr
After completion of the shoring and removal of the soils to subgrade elevation, the site
earthwork is expected to consist of excavating foundations, installing under slab utilities
and preparing the slab subgrade. Parking area earthwork is expected to consist of grading,
underground utility installation and preparing parking subgrades.
5.3.1 Srr PRepnnlnoru
Subgrade soils that become disturbed due to elevated moisture conditions should be
overexcavated to reveal firm, non-yielding, non-organic soils and backfilled with
compacted structural fill. lf earthwork is completed during the wet season (typically
November through May) it will be necessary to take extra precautionary measures to
protect subgrade soils. Wet season earthwork will require additional mitigative measures
beyond that which would be expected during the drier summer and fall months.
5.3.2 SrnucruRal Ftl
RGI recommends fill below the foundation and floor slab, behind retaining walls, and below
pavement and hardscape surfaces be placed in accordance with the following
recommendations for structural fill.
ltrTTI
RILEYGR()UP
Geotechnical Engineering Report page 13
Jefferson Healthcare South Campus, Port Townsend, Washington
January t2,2O23
RGI Project No. 2022-387-1
The suitability of excavated site soils and import soils for compacted structural fill use will
depend on the gradation and moisture content of the soil when it is placed. As the amount
of fines (that portion passing the U.S. No. 200 sieve) increases, soil becomes increasingly
sensitive to small changes in moisture content and adequate compaction becomes more
difficult or impossible to achieve. Soils containing more than about 5 percent fines cannot
be consistently compacted to a dense, non-yielding condition when the moisture content
is more than 2 percent above or below optimum. Optimum moisture content is that
moisture that results in the greatest compacted dry density with a specified compactive
effort.
Non-organic site soils are only considered suitable for structural fill provided that their
moisture content is within about 2 percent of the optimum moisture level as determined
by American Society of Testing and Materials D1557-09 Standard Test Methods for
Laboratory Compaction Characteristics of Soil Using Modified Effort (ASTM D1557).
Excavated site soils may not be suitable for re-use as structural fill depending on the
moisture content and weather conditions at the time of construction. lf soils are stockpiled
for future reuse and wet weather is anticipated, the stockpile should be protected with
plastic sheeting that is securely anchored.
Even during dry weather, moisture conditioning (such as, windrowing and drying) of site
soils to be reused as structural fill may be required. Even during the summer, delays in
grading can occur due to excessively high moisture conditions of the soils or due to
precipitation. lf wet weather occurs, the upper wetted portion of the site soils may need
to be scarified and allowed to dry prior to further earthwork, or may need to be wasted
from the site.
The site soils are moisture sensitive and may require moisture conditioning prior to use as
structural fill depending on the time of year and weather conditions at the time of
excavation. lf on-site soils are or become unusable, it may become necessary to import
clean, granular soils to complete site work. Prior to rlse, an RGI representative should
observe and test all materials imported to the site for use as structural fill. Structural fill
materials should be placed in uniform loose layers not exceeding 12 inches and compacted
to 95 percent of the maximum dry density. The soil's maximum density and optimum
moisture should be determined by ASTM D1557.
Placement and compaction of structural fill should be observed by RGl. A representative
number of in-place density tests should be performed as the fill is being placed to confirm
that the recommended level of compaction is achieved.
5.3.3 Wrr Wunrnen CorusrRuciloN CoNslDERATloNs
RGI recommends that preparation for site grading and construction include procedures
intended to drain ponded water, control surface water runoff, and to collect shallow
llrlrI
RILEYGR{]UP
Geotechnical Engineering Report Page 14
Jefferson Healthcare South Campus, Port Townsend, Washington
)anuary 12,2023
RGI Project No. 2022-387-1
subsurface seepage zones in excavations where encountered. lt will not be possible to
successfully compact the subgrade or utilize on-site soils as structural fill if accumulated
water is not drained prior to grading or if drainage is not controlled during construction.
Attempting to grade the site without adequate drainage control measures will reduce the
amount of on-site soil effectively available for use, increase the amount of select import fill
materials required, and ultimately increase the cost of the earthwork phases of the project.
Free water should not be allowed to pond on the subgrade soils. RGI anticipates that the
use of berms and shallow drainage ditches, with sumps and pumps in utility trenches, will
be required for surface water control during wet weather and/or wet site conditions.
5.4 Fouruolnorus
Following installation of the shoring and excavation to design grades, the proposed building
foundation can be supported on conventional spread footings bearing on dense native soil
or structural fill. On the east side of the proposed building, micropiles will be used for
foundation support to avoid loading of an existing retaining wall for the adjacent structure.
5.4.1 SnauowFouNDATtoNs
We expect most foundations will be excavated into the dense native soils. lf unsuitable
soils are encountered at foundation subgrade, they should be overexcavated and backfilled
with structural fill or lean mix concrete if the native soil bearing pressure is used.
Perimeter foundations exposed to weather should be at a minimum depth of 18 inches
below final exterior grades. lnterior foundations can be constructed at any convenient
depth below the floor slab. Finished grade is defined as the lowest adjacent grade within 5
feet of the foundation for perimeter (or exterior) footings and finished floor level for
interior footings.
Table 3 Foundation Design
Design Parameter Value
Allowable Bearing Capacity - Structural Fill
Dense native soils
Friction Coefficient
Passive pressure (equivalent fluid pressure)
Minimum foundation dimensions
2,500 psfl
4,000 psf
0.30
25O pcf2
Columns: 24 inches
Walls: 16 inches
1. psf = pounds per square foot
2. pcf = pounds per cubic foot
ttI!rI
RILEYGR{]UP
Geotechnical Engineering Report Page 15
Jefferson Healthcare South Campus, Port Townsend, Washington
Januarv 12,2023
RGI Project No. 2022-387-1
The allowable foundation bearing pressures apply to dead loads plus design live load
conditions. For short-term loads, such as wind and seismic, a 1/3 increase in this allowable
capacity may be used. At perimeter locations, RGI recommends not including the upper 12
inches of soil in the computation of passive pressures because they can be affected by
weather or disturbed by future grading activity. The passive pressure value assumes the
foundation will be constructed neat against competent soil or backfilled with structural fill
as described in Section 5.3.2. The recommended base friction and passive resistance value
includes a safety factor of about 1.5.
With spread footing foundations designed in accordance with the recommendations in this
section, maximum total and differential post-construction settlements of 1 inch and 1/2
inch, respectively, should be expected.
5.4.2 Mrcnoprtes
For Micropiles designed in accordance with FHWA-SA-97-O7O,the following capacities may
be used for the dense to very dense soils encountered on the site in the vicinity of the
proposed piles. Based on the proximity of the piles to the existing wall, the capacity of the
piles should be limited to the portion below the wall footing and should be installed to
prevent additional soil loads above the foundation level. Based on our experience with
similar glacial soils, the soils should not be corrosive.
Table 4 Micropile Design Parameters
Grout-to-Ground Bond Nominal Strengths (ksfl
Soils
Type B to D
Dense to very dense silty sand
glacial till
Type A - Gravity grout only
Type B - Pressure grouted through the casing during casing withdrawal
Type C - Primary grout placed under gravity head, then one phase of secondary "global" pressure grouting
Type D - Primary grout placed under gravity head, then one or more phases of secondary "global" pressure grouting
Micropiles should be tested to confirm capacities of the installed piles. At least one
performance test should be completed to 2.5 times the design load and 5 percent of the
total number of production piles should be proof tested to 1'67 times the design load.
5.5 RerRrrurne WRU-s
RGI expects the below grade level basement walls will be formed directly against shoring
in some areas. lf retaining walls are needed as part of the building, RGI recommends cast-
in-place concrete walls be used. lf walls are needed for grade changes outside of the
building, modular block walls may be used. Based on the recent site plan, modular block
walls will be used for grade changes for the parking areas. The design and construction
5
rlIlrI
RILEYGR()UP
Type A
2
Geotechnical Engineering Report Page 16
Jefferson Healthcare South Campus, Port Townsend, Washington
January 12,2O23
RGI Project No. 2022-387-1
recommendations for these walls will be provided as a separate document for permit
submittal for the walls.
5.5.1 Penrunrurrur Beseruerut Weu-s
The basement walls formed against cantilever soldier pile and tieback shoring should be
designed for the earth pressures provided on Figures 3 through 5 and any surcharges.
Permanent basement walls formed against soil nail shoring should be designed for the
values in Table 5 below and any surcharges. An additional earthquake load of 7H should be
added to the full wall height. Permanent basement walls formed against shoring should be
provided with drainage. A typical drainage system for walls formed against shoring is
attached as Figure 7.
5.5.2 Rrrntrutne Wnu Desteru
The magnitude of earth pressure development on retaining walls will partly depend on the
quality of the wall backfill. RGI recommends placing and compacting wall backfill as
structural fill. Wall drainage will be needed behind the wall face. Typical drainage for slope
cut wall is shown on Figure 8.
With wall backfill placed and compacted as recommended, and drainage properly installed,
RGI recommends using the values in the following table for design.
Table 4 Retaining Wall Design
Design Parameter Value
Active Earth Pressure (unrestrained walls)35 pcf
At-rest Earth Pressure (restrained walls)50 pcf
For seismic design, an additional uniform load of 7 times the wall height (H) for
unrestrained walls and 14H for restrained walls should be applied to the wall surface.
Friction at the base of foundations and passive earth pressure will provide resistance to
these lateral loads. Values for these parameters and allowable bearing are provided in the
Foundations section of this GER.
5.6 SLne-oN-GRADECoNsrRUcnoN
Once site preparation has been completed as described in Section 5.3, suitable support for
slab-on-grade construction should be provided. RGI recommends that the concrete slab be
placed on top of medium dense native soil or structural fill. lmmediately below the floor
slab, RGI recommends placing a 4-inch-thick capillary break layer of clean, free-draining
sand or gravel that has less than five percent passing the U.S. No. 200 sieve. This material
will reduce the potential for upward capillary movement of water through the underlying
rlrtr!
RILEYGR(1UP
Geotechnical Engineering Report page 17
Jefferson Healthcare South Campus, Port Townsend, Washington
January 12,2023
RGI Project No. 2022-387-1
soil and subsequent wetting of the floor slab. Where moisture by vapor transmission is
undesirable, an 8- to L0-millimeter-thick plastic membrane should be placed on a 4-inch-
thick layer of clean gravel.
For the anticipated floor slab loading, we estimate post-construction floor settlements of
L/4- to L/2-inch. For thickness design of the slab subjected to point loading, RGI
recommends using a subgrade modulus (Ks) of 150 pounds per square inch per inch of
deflection.
5.7 Dnatruner
5.7.L SuRrncr
Final exterior grades should promote free and positive drainage away from the building
area. Water must not be allowed to pond or collect adjacent to foundations or within the
immediate building area. For non-pavement locations, RGI recommends providing a
minimum drainage gradient of 3 percent for a minimum distance of 10 feet from the
building perimeter. ln paved locations, a minimum gradient of 1 percent should be
provided unless provisions are included for collection and disposal of surface water
adjacent to the structure.
5.7.2 SuesuRrece
RGI recommends installing perimeter drainage as shown on Figures 7 ,8, and 9. At the time
this GER was prepared, the configuration of the below grade levels was not known. RGI
should be contacted to provide additional recommendations for below grade drainage
once the below grade plans are completed.
The foundation drains and roof downspouts should be tightlined separately to an approved
discharge facility. Subsurface drains must be laid with a gradient sufficient to promote
positive flow to a controlled point of approved discharge.
5.7.3 lrunlrRnnoru
Two small-scale Pilot lnfiltration Test (PlT) was performed at the site. lnfiltration test INF-1
was completed on the southern portion of the property and INF-2 was completed on the
eastern portion of the property, east of the existing paved parking area. lnfiltration test
INF-1 was completed at a depth of approximately 3.5 feet below grade with the infiltration
test pit measuring 2 feet by 6 feet. lnfiltration test INF-2 was completed at a depth of
approximately 3 feet below grade with the infiltration test pit measuring 2 feet by 6 feet.
The small scale Pilot lnfiltration Tests (PlT) was completed in accordance with the 2014
Washington State Department of Ecology Stormwater Management Manual for Western
Washington (SMMWW).
!lrtrI
RITEYGR()UP
Geotechnical Engineering Report Page 18
Jefferson Healthcare South Campus, Port Townsend, Washington
Table 5 Measured lnfiltration Rates
Field Measured Rate
(inches/hour)
January 12,2023
RGI Project No. 2022-387-1
Ksat Design Rate
(inches/hourlTest Location Test Depth (feetl
INF-1 3.2
INF-2 0.9
Correction factors in the SMMWW were applied to the field measured infiltration rate (K'"t
initial) to determine long-term design infiltration rates. Correction factors include factors
for uncertainties in site variability, test method, and degree of influent control.
Calculotion oI Krot design
CF1=fPuxCFtxCFm
6Pt = (0.7)x (0.50) x (0.9) =O.32
Where:
CFr = Total Correction Factor
CFv = Site variability and number of locations tested (0.7)
CFt = 0.5 for small-scale PIT test
CFn. = 0.9 for influent control and bio-buildup
RGI understand permeable pavement is planned in the area where the infiltration testing
was completed. The above design rates exceed the minimum rate of 0.30 inches/hour to
support permeable pavement.
5.8 Urtunes
Utility pipes should be bedded and backfilled in accordance with American Public Works
Association (APWA) specifications. For site utilities located within the right-of-ways,
bedding and backfill should be completed in accordance with City of Port Townsend
specifications. At a minimum, trench backfill should be placed and compacted as structural
fill, as described in Section 5.3.2. Where utilities occur below unimproved areas, the degree
of compaction can be reduced to a minimum of 90 percent of the soil's maximum density
as determined by ASTM D1557. As noted, soils excavated on site should be suitable for use
as backfill material provided earthwork takes place in the summer and fall months in dry
weather. lf site soils become unusable, clean (less than 5 percent fines) imported structural
fill should be used for trench backfill.
ltrlrI
RILEYGR(]UP
10.03.5
3.0 2.75
Geotechnical Engineering Report page 19
Jefferson Healthcare South Campus, Port Townsend, Washington
'lanuaryL2,2023
RGI Project No. 2022-387-1
5.9 PRvrnnerurs
Pavement subgrades should be prepared as. described in Section 5.3 and as discussed
below. Regardleis of the relative compaction achieved, the subgrade must be firm and
relatively unyielding before paving. The subgrade should be proof-rolled with heavy
construction equipment to verify this condition.
5.9.1 FlexreLePnveurrurs
With the pavement subgrade prepared as described above, RGI recommends the following
pavement sections for parking and drive areas paved with flexible asphalt concrete
surfacing.
5.9.2 CotcRrrePnvemrnrs
With the pavement subgrade prepared as described above, RGI recommends the following
pavement sections for parking and drive areas paved with concrete surfacing.
The paving materials used should conform to the WSDOT specifications for HMA, concrete
paving, and CRB surfacing (9-03.9(3) Crushed Surfacing).
Long-term pavement performance will depend on surface drainage. A poorly-drained
pavement section will be subject to premature failure as a result of surface water
infiltrating into the subgrade soils and reducing their supporting capability.
For optimum pavement performance, surface drainage gradients of no less than 2 percent
are recommended. Also, some degree of longitudinal a.nd transverse cracking of the
pavement surface should be expected over time. Regular maintenance should be planned
to seal cracks when they occur.
6.0 Additionalservices
RGI is available to provide further geotechnical consultation throughout the design phase
of the project. RGI should review the final design and specifications in order to verify that
earthwork and foundation recommendations have been properly interpreted and
incorporated into project design and construction.
RGI is also available to provide geotechnical engineering and construction monitoring
services during construction. The integrity of the earthwork and construction depends on
proper site preparation and procedures. ln addition, engineering decisions may arise in the
field in the event that variations in subsurface conditions become apparent. Construction
monitoring services are not part of this scope of work.
ItrlrI
RILEYGR()UP
Geotechnical Engineering Report
Jefferson Healthcare South Campus, Port Townsend, Washington
Page 20 lanuarv t2,2023
RGI Project No. 2022-387-1
7.O Limitations
This GER is the property of RGl, Jefferson Healthcare, and its designated agents. Within the
limits of the scope and budget, this GER was prepared in accordance with generally
accepted geotechnical engineering practices in the area at the time this GER was issued'
This GER is intended for specific application to the Jefferson Healthcare South Campus
Replacement and Addition project in Port Townsend, Washington, and for the exclusive
use of Jefferson Healthcare and its authorized representatives. No other warranty,
expressed or implied, is made. Site safety, excavation support, and dewatering
requirements are the responsibility of others.
The scope of services for this project does not include either specifically or by implication
any environmental or biological (for example, mold, fungi, bacteria) assessment of the site
or identification or prevention of pollutants, hazardous materials or conditions. lf the
owner is concerned about the potential for such contamination or pollution, we can
provide a proposal for these services.
The analyses and recommendations presented in this GER are based upon data obtained
from the test exploration performed on site. Variations in soil conditions can occur, the
nature and extent of which may not become evident untilconstruction. lf variations appear
evident, RGI should be requested to reevaluate the recommendations in this GER prior to
proceeding with construction.
It is the client's responsibility to see that all parties to the project, including the designers,
contractors, subcontractors, are made aware of this GER in its entirety. The use of
information contained in this GER for bidding purposes should be done at the contractorls
option and risk.
trIlr!
RILEYGR(]UP
ICTO
T
STH/
l,I
4THsrl*
F-t-?
=<d
LI
E
UJ:ttn
5TI
5rH
('tgE
l"l
I.JJftz.q
-J
e
-ili-
-t li-
.-!l 1
1-*{$lr
0rH 5r
9rH 5r {
5
a(q
l_U
rjl
sl
.ld
T-]
IJJ
r-J
F*.n
]ta,
>
q')q
LU
TJ0lJ
4_q
.I
H.L4
l-trl
(/){Es
.t-
t*-
I
L a,..J*t,,tfJ
I ltc.1 j
USGS, 2O2O, Port Townsend South, Washington
7.5-Minute Quadrangle
Approximate Scale: 1"=1000'A
N0 500 1000ITIlr!
RILEYGR()UP
Bothell, Washington 98011
Phone: 425.415.0551
Fax: 425.415.0311 Address: 834 Sheridan Street, Port Townsend, Washington 98368
Healthcare South Campus Replacement and Addition Figure 1
Site Vicinity MapRGI Project Number:
2022-387-7
Date Drawn:
09/2022
Corporate Office
17522 Bothell Way N
.Fqr *f
r!*
i5-r)'a
UINFl
a
P'*"$
-l
*.l
nt
p
,t "rOl*i,F
t
I
,L
iq Eet '{r '*
f-.
.. .. i ,-J,\
f---tF-''-*.f..
+*
---B :F
!.1 ,:i {
I
I'l
'-l
I
I
fr,
1,
lib
il,:1
IN F2
B
tri
,f-
,{t <*F.r
?
4
l:'-4
t '_J )
r;
S-Su t
L .'-*.t {:, .-l
-
t
I
" ilt
/f ,'r{iF,t
rfu*#-
r
i,j'I1
L
'.t
!F.
*"T
#{ ..1-Ltf ,'
i L
a
+{-: *!-*
i
1
i=!4r:!!fiiid[,1 !
.a*r?
,t':ltiilt-ol:' a*4 f*
['ffr,#"
E = lnfiltration test by RGl, 07/04/2023
$ = Boring by RGl, o8l3o-31/2022
--- =SiteboUndary
Approximate Scale: 1" l-80'A
N0 90 180 360
:1
t
.4 ?
*r'I I'Ff {
{.
I
Jefferson Healthcare South Campus Replacement and Additio Figure 2
Date Drawn
a912022
RGI Project Number:
2022-387-t Geotechnical Exploration Plan
Address: 834 Sheridan Street, Port Townsend, Washington 98368
I I I:IHT::fllllfayNortheas,
I f ! Rnrnerr nrasnrnsrnn Yir-ri r
iln ffe nIIF illX"; li? ;1 ll,T "
Hs
R
35 pcf
Hw
75 psf
(Traffic Surcharge
where applicable)
Base of Excavation
2',
a00(D) psf
DesignHeight: H=Hw+Yz
Notes:
L. Apparent earth pressure and surcharge act overthe pile spacing above the base ofthe excavation.
2. Passive earth pressure acts over 2 times the concreted diameter of the soldier pile, or the pile spacing whichever is less.
3. Passive pressure includes a reduction factor.
4. Additional surcharge from footings of adjacent buildings should be included.
5. This pressure diagram is appropriate for temporary soldier pile walls. lf additional surcharge loading (such as from soil
stockpiles, excavators, dumptrucks, cranes, or concrete trucks) is anticipated, RGI should be consulted to provide revised
surcharge pressures.
Not to Scale
g'
D
Jefferson Healthcare South Campus Replacement and Additio Figure 3
RGI Project Number:
2022-387-L Soldier Pile Pressure Diagram Date Drawn:
a9/2022! I : ;;,=-.; ;;;^,*="u *o..n"".,
ru Fv e nbIF il-l l;,1ii ;1 ll i,"'Add 834 shend Street,Port Townsend,Wash ington 983 68ress:na
Geotechnical Engineering Report
Jefferson Healthcare South Campus, Port Townsend, Washington
January 12, 2023
RGI Project No. 2022-387-1
APPENDIX A
FIETD EXPTORATION AND TABORATORY TESTING
On August 30 and 3L,2022, RGI performed field explorations using a track rig. RGI explored
subsurface soil conditions at the site by observing the drilling of 10 borings to a maximum
depth of 21.5 feet below existing grade. Additionally, RGI performed 2 infiltration test pits
using a mini excavator on January 4,2023. All the boring and test pit locations are shown
on Figure 2. Exploration locations were approximately determined by measurements from
existing property lines and paved roads.
A geologist from our office conducted the field exploration and classified the soil conditions
encountered, maintained a log of each test exploration, obtained representative soil
samples, and observed pertinent site features. All soil samples were visually classified in
accordance with the Unified Soil Classification System (USCS).
Representative soil samples obtained from the explorations were placed in closed
containers and taken to our laboratory for further examination and testing. As a part of the
laboratory testing program, the soil samples were classified in our in-house laboratory
based on visual observation, texture, plasticity, and the limited laboratory testing described
below.
Moisture Content Determinations
Moisture content determinations were performed in accordance with ASTM D22L6-IO
Standard Test Methods for Laboratory Determination of Water (Moisture) Content of Soil
and Rock by Mass (ASTM D2216) on representative samples obtained from the exploration
in order to aid in identification and correlation of soil types. The moisture content of typical
sample was measured and is reported on the boring Logs.
Grain Size Analysis
Agrain size analysis indicatesthe range in diameter of soil particles included in a particular
sample. Grain size analyses was determined using D6913-04(2009) Standard Test Methods
for Particle-Size Distribution (Gradation) of Soils Using Sieve Analysis (ASTM D6913) on two
of the samples.
!!!
Project Name: Jefferson Healthcare South Campus
Project Number: 2022-387 -1
Client: Jefferson Healthcare
165
llrlt!
RILEYGRt}UP
Test Pit No.: INF-1
0)d)
-co.o)o
c)(t)
c.9o
o
lu
't70
The Riley croup, lnc.'17522 Borhell Way NE, Bothel, wA 9801 1
Date(s) Excavated: 1 l4l2023 Logged By ELW Surface Conditions: Grass
Excavation Method: Test Pit Bucket Size: N/A Total Depth ofExcavation: 3.5 feet bgs
Excavator Type: Mini Excavator Excavating Contractor: Kelly's Excavating !nx'd11i;",,"" rzo
Groundwater Level: Not Encountered Sampling
Method(s)Compaction Method Bucket
Test Pit Backfill: Cuttings Location 834 Sheridan Street, Port Townsend, Washington
o)o
F
_9o
Eo(t)
ct-oE
z
_9CL
EIEa)
E-oE
u)aoU)l
o)oJ
.9
CL(g
o MATERIAL DESCRIPTION REMARKS AND OTHER TESTS
6 2"
SM
Fiil Brown silty SAND with some gravel, loose to medium
dense, moist (Fiil)
Tan silty SAN with some gravel, dense, moist
Test Pit terminated at 3.5'
lnfiltration test performed at
3.5'
,l
Project Name: Jefferson Healthcare South Campus
Project Number: 2022-387 -1
Client: Jefferson Healthcare
Irt Test Pit No.: INF-2IIII
RILEY6Rl)I'P
Date(s) Excavated: 1 l4l2|23 Logged By ELW Surface Conditions: Grass
Excavation Method: Test Pit Bucket Size: N/A Total Depth of Excavation:
Excavator Type: Mini Excavator Excavating Contractor: Kelly's Excavating Approximate
Surface Elevation
Groundwater Level: Not Encountered Sampling
Method(s)CompactionMethod Bucket
Test Pit Backfill: Cuttings Location 834 Sheridan Street, Port Townsend, Washington
od)
E
o-IDo
o)o)
c.9o
o)
lrJ REMARKS AND OTHER TESTS
oo.
F
-gCI
E(!a
o-oE
z
0)
EoU)
o-oE
U)aou)l
o)oJ
.c)Eogo MATERIAL DESCRIPTION
SW.SM 4" topsoil
SM
SM Reddish brown silty SAND with some gravel, loose to
medium dense, moist
Gray silty SAND with some gravel, dense, moist
-Becomes tan
(Glacial
Tiil)
lnfiltration test at 3'
Test Pit terminated at 6'
The Riley Group, lnc.
17522 Bothell Way NE, Bothell, WA 98011
Project Name: Jefferson Healthcare South Gampus
Project Number: 2022-387 -1
Client: Jefferson Healthcare
COLUMN DESCRIPTIONS
Elevation (feet): Elevation (MSL, feet).
Depth (feet): Depth in feet below the ground surface.
Sample Type: Type of soil sample collected at the depth interval
shown.
@ Sampte Number: Sample identification number
FIELD AND LABORATORY TEST ABBREVIATIONS
CHEM: Chemical tests to assess corrosivity
COMP: Compaction test
CONS: One-dimensional consolidation test
LL: Liquid Limit, percent
MATERIAL GRAPHIC SYMBOLS
USCS Symbol: USCS symbol of the subsurface material.
Graphic Log: Graphic depiction of the subsurface material
encountered.
@ Unfentm DESCRIPTION: Description of material encountered.
May include consistency, moisture, color, and other descriptive
text.
@ neHlnnfs AND OTHER TESTS: Comments and observations
regarding drilling or sampling made by driller or field personnel.
Pl: Plasticity lndex, percent
SA: Sieve analysis (percent passing No. 200 Sieve)
UC: Unconfined compressive strength test, Qu, in ksf
WA: Wash sieve (percent passing No. 200 Sieve)
Silty SAND (SM)
Well graded SAND with Silt (SW-SM)
rtIlrI
RILEYGR()UP
Key to Logs
ffi AF
Auger sampler
Bulk Sample
3-inch-OD California w/
brass rings
ffi "t. samprer
TYPICAL SAMPLER GRAPHIC SYMBOLS OTHER GRAPHIC SYMBOLS
Pitcher Sample - Water level (at time of drilling, ATD)
2-inch-oD unlined split j water level (after waiting' AW)
spoon (SPT) - Minor change in material properties within aV stratum
Shelby Tube (Thin-walled, - tnferred/gradational contact between stratafixed head)
-?- Queried contact between strata
t
N
X
n
ffi
Mn
Grab Sample
2.5-inch-OD Modified
California w/ brass liners
GENERAL NOTES
1: Soil classifications are baJed on the Unified Soil Classification System. Descriptions and stratum lines are interpretive, and actual lithologic changes may begradual. Field descriptions may have been modified to reflect results of lab tests.
2: Descriptions on these logs apply only at the specific boring locations and at the time the borings were advanced. They are not warranted to be representativeof subsurface conditions at other locations or times.
The Riley croup, Inc.
17522 Bolhell Way NE, Bothell, WA 9801 1
od)
.9
(E
{l)
lrJ
o)d)
E
CLo)o
o)o
F
c)
CIEou)
o-oEz
_g
CL
EGa
6-oEaaoU)f
o)oJ
.o
o-(E(,MATERIAL DESCRIPTION REMARKS AND OTHER TESTS
I
Project Name: Jefferson Healthcare South Gampus
Project N u mber: 2022-387 -1
Client: Jefferson Healthcare
I!Boring No.: B-1
Sheet 1 ol 2
lllr
RILEYGR()UP
Date(s) Drilled: 8l3Ol2O22 Logged By: ELW Surface Conditions: Grass
Drilling Method(s): Hollow Stem Auger Drill Bit Size/Type: 8" auger Total Depth ol Borehole: 21.5 feet bgs
Drill Rig Type: Track Rig Drilling Contractor: Bortec Approximate
Surface Elevation:179
Groundwater Level: 21'Sampling Method(s): SPT Hammer Data 140 lb, 30" drop, rope and
cathead
Borehole Backtill: Well lnstalled Location: 834 Sheridan Street, Port Townsend, Washington
c)(l,
o.oo
n
0)o
Eo
(d
-9IU
179
s
o
.9o
o)oJ
o3
;9-o
o(JoE.
o_o
E
aaOal
o,oJ
.oco(d
o MATERIAL DESCRIPTION
oo
FooE({a
o
o)
o_
E(da
o.)ocd
.9U)0)Eo,
E_bE}do@v
TPSL
aa/a/
/a/aaaa,aa,/
11
IJ
1417
25
23
65
SM
Topsoil
-?rafmoilted
"iliv Sruo wit|r traG sEvetFedTumGnG mo-ist @taffit -
- Tilr)
-Becomes very dense, contains 1" sand lens with iron oxide staining16910
The Rilsy Group, lnc.
17522 Bothell Way NE, Bothell, WA 98011
'15
Project Name: Jefferson Healthcare South Campus
Project Number: 2022-387 -1
Client: Jefferson Healthcare
trrlr!
RILEYGROUP
Boring No.: B-1
Sheet 2 ol 2
o)c)
c(1oo
15
o)d)
c.9(!
o
TJJ
164
159 20
154 25
The Riley Group, lnc.
17522 Bothell Way NE, Bothell, WA 9801i
oo
FoE
Eda
o
-go_
E(Ua
ooc.(d
-tho(l)
TE
o)
O" utE=do@.8
s
bo
oooE,
ooE
U)
Qoaf
(')oJ
.9
o.(U(,MATERIAL DESCRIPTION
s
o
5
.9,o
o)oJ
6
=
S
SM
SM
Gray Silty SAND with trace gravel, very dense, moist (clacial-ill)-
-drafiirtlEnrrr6 uuTF tri6e dlaufrverv oe-nse,
i
wet
-16% lines
-Becomes water bearing
50/6'
88
Boring terminated at 21.5'
10
13
30
-)-)
II Boring No.: B-2
Sheet 1 of 1
tI tI
RILEYGROUP
Project Name: Jefferson Healthcare South Gampus
Project Number: 2022-387 -1
Client: Jefferson Healthcare
Date(s) Drilled : 8l30l 2022 Logged By: ELW Surface Conditions: Asphalt
Drilling Method(s): Hollow Stem Auger Drill Bit Size/Type: 6" auger Tolal Depth ol Borehole: 11.42 feet bgs
Drill Rig Type: Track Rig Drilling Contractor: Bortec Approximate
Surface Elevalion:180
Groundwater Level: Not Encountered Sampling Method(s): SPT Hammer Data 140 lb,30" drop, rope and
cathead
Borehole Backlill: Cuttings Location: 834 Sheridan Street, Porl Townsend, Washington
oo
oo)o
oo
c.9
(d
o
uJ
180
5
o)oJ
o3
;s
o5
.oo
f
:.ct
oooE.
6-oE
a(/)o(t)f
o)oJ
.9Eago MATERIAL DESCRIPTION
(Do
F
-go
E(!a
o
-eo
E(Ua
0)oc(d
-9.IJ'oE.
o)
o-@E=(!oA.o
S
TrayTirtv-Snn-owitntriiegr"ufr urto"*e,ioist-(ciEiiaiJill)---
4" asphalt over washed rock
-22o/" lines
\sphall
SM
a
9
7
I
50/6"
86/t 1"
54
ao
Boring terminated at 1l'5"
't70
Ths Ril€y Group, lnc.
17522 Bothell way NE, Bothell, WA 98011
15
Project Name: Jefferson Healthcare South Gampus
Project Nu mber: 2022-387 -1
Client: Jefferson Healthcare
I t I Borinq No.: B-3
t "1t sneer r or r
Date(s) Drilled: 813012022 Logged By: ELW Surface Conditions: Gtass
Drilling Method(s): Hollow Stem Auger Drill Bit Size/Type: 6" auger Total Depth ol Borehole: 10.92 leet bgs
Drill Rig Type: Track Rig DrillingContractor: Bortec Approximate
Surface Elevalion: l'o
Groundwater Level: Not Encountered Sampling Method(s): SPT Hammer Data 1 40 lb, 30' drop, rope and
Borehole Backfill: Cufiings Location: 834 Sheridan Street, Port Townsend, Washington
oo
E
o-oo
oto
c.9
(U
o)
uJ
't78
o
-qo.
E(!a
ooE(d
.q.thctE
ct)
cLdE}do@v
*
bo
ooocc
6c
E
U)
@()
U)
O)oJ
.o-co_6o MATERIAL DESCRIPTION
t')oJ
o
=
s
o
5
-ato
TPSL
SM
SM sntto wittr trace graG, miaiuF o6'se-, rnoiii
-crayf irtv-Sar'tTw-nntriiegravfr veryoinse,-moiil(o-uciaiTil)---
I Topsoil
l-__
Brown silty
I
50/5"
21
54
51
Boring terminated at 10'1 1"
4
5
7
7
The Riley Group, lnc.'17522 Bolhell Way NE, Both6ll, WA 9801 |
,J "a}
Boring No.: B-4
Sheet 1 of 1
rlrtr!
RILEYGR()UP
Project Name: Jefferson Healthcare South Gampus
Project Number: 2022-387 -1
Client: Jefferson Healthcare
Date(s) Drilled: I l3Ol2O22 Logged By: ELW SurfaceConditions: Grass
Drilling Method(s): Hollow Stem Auger Drill Bit Size/Type: 8" auger Total Depth of Borehole: 10.92 feet bgs
Drill Hig Type: Track Rig Drilling Contractor: Bortec Approximate
Surface Elevation:160
Groundwater Level: Not Encountered Sampling Method(s): SPT Hammer Data 140 lb, 30'drop, rope and
cathead
Borehole Backlill: Well lnstalled Location: 834 Sheridan Street, Port Townsend, Washington
oo
-co.oo
oo
co
(d
-9UJ
I
155
'10
The Riley Group, lnc.
17522 Bothell Way NE, Bothell, WA 9801 1
;e
o5
th'6
o)o
-J
0)3
o)oJ
.(J-co-(U
o MATERIAL DESCRIPTION
cto
FooEda
o
o
o_
Eda
(lt()Cd
.9U)0)E
o)
o_6E}doaz
-b<
t'o
o()otr
o_o
Ea
U)Oa:)
TPSL
SM
Fitl
loose lo medium dense, trace brick debris
very dense
gravel, dense Eoiilcuaialr_ritt)withSAND tracesilty
, moisttracewithlooseBrownSAND (Fiil)silty gravel,
Topsoil
10
9
8
.,
Boring terminated at
50/5'
10
7
35
145 15
Project Name: Jefferson Healthcare South Gampus
Project Number: 2022-387 -1
Client: Jefferson Healthcare
Boring No.: B-5
Sheet 1 of 1
II
RILEYGROUP
ltlr
Date(s) Drilled: 813012022 Logged By: ELW Surface Conditions: Gravel
Drilling Method(s): Hollow Stem Auger Drill Bit SizeiType: 6" auger Total Depth of Borehole: 11.5 feet bgs
Drill Rig Type: Track Rig DrillingContractor: Bortec !P';i11i;,,,"", roo
Groundwaler Level: Not Encountered Sampling Method(s): SPT Hammer Data 140 lb,drop, rope and
Borehole Backfill: Benlonite Chips Location: 834 Sheridan Street, Port Townsend, Washington
oo
E
o-oo
o(1)
c.9
(E
o
I.JJ
'1
o)o
FgoE(da
o
-qo.Eda
0)oc(d
.o6oE
O)
EbE}do@6
s
o
ooo)E.
E-oE
u)
ct)oat)f,
o)oJ
.o-co-
Eo MATERIAL DESCRIPTION
o)oJ
ot3
be
o5
.9o
SM
Fiil
with trace gravel, medium dense, moist (Glacial Till)
-Becomes medium dense
-Becomes very dense
Brown silty SAND with trace gravel, loose, moist (Fill)
Gray silty SAND
I
13
29
67
Boring terminated at 1 1' 6"
10
b
'10
The Biley Group, lnc.'17522 Bothell Way NE, Bothell, WA 98011
'l
Project Name: Jefferson Healthcare South Gampus
Project Number: 2022-387 -1
Client: Jefferson Healthcare
t I I Boring No.: B-6
;',},ffi sheet 1 or 1
Date(s) Drilled: 8l3Ol2O22 Logged By: ELW Surface Conditions: Gravel
Drilling Method(s): Hollow Stem Auger Drill Bit Size/Type: 6" auger Total Depth of Borehole: 11.5 feet bgs
Drill Rig Type: Track Rig Drilling Contractor: Bortec Approximate
Surface Elevalion:170
Groundwaler Level: Not Encountered Sampling Method(s): SPT Hammer Data 140 lb, 30" drop, rope and
cathead
Borehole Backfill: Bentonite Chips Location: 834 Sheridan Street, Pott Townsend, Washington
o)(t
o_c)C]
0
oo
go
(d
-0)
I.JJ
170
165
10
The Riley Group, lnc.
17522 Bolhell Way NE, Bothell, WA 98011
s
o
.9o
=
o)oJ
o3MATERIAL DESCRIPTION
oo
F
-qoEda
o
o
o_
Eda
0)()cd
.9oo)E
o)
E_bE}do6E
Ebo)
oooE.
o-oEa
u)oaf,
o)o
-J.o.c,o-(!(t
I PSL
Gray silty SAND with trace gravel, very
Topsoil
medium dense, moist
dense, moist (Glacial Till)
Brown silty SAND with trace gravel,
SM
SM
't1
I
I
Boring terminated at 1 1' 6"
89/1 1.
17
77
82
155 15
Project Name: Jefferson Healthcare South Gampus
Project Number: 2022-387 -1
Client: Jefferson Healthcare
166
161
I!Boring No.: B-7
Sheet 1 of 1
Itlr
RILEYGRt)UP
oo
o.q,o
0
oo
co
(g
-9u-l
171
The Riley Group, lnc.'17522 Bothell Way NE, Bothell, WA 9801 1
Date(s) Drilled: 8l3Ol2O22 Logged By: ELW Surface Conditions: Gravel
Drilling Method(s): Hollow Stem Auger Drill Bit SizeiType: 6" auger Total Depth of Borehole: 10.42 feet bgs
Drill Rig Type: Track Rig DrillingContractor: BofieC Approximate
Sudace Elevalion:171
Groundwater Level: Not Encountered Sampling Method(s): SPT Hammer Data 140 lb, 30" drop, rope and
Borehole Backlill: Bentonite Chips Location: 834 Sheridan Street, Port Townsend, Washington
o)o
Foo
ErdU)
o
_eo.
E(ga
c)oc(d
.@IJ'oE(')
o-d,E}(60av
be
bo
oooE
Eo
EaaO
<t)f
cto-).9
o-(U(,MATERIAL DESCRIPTION
o)o
-J
ct3
s
o
=.u,o
TPSL T
SM
SM
-oafiirti5nrvD w-itn trii" gavet, vetoens",Toist-(ciliiaiTill)- - -
Topsoil
t-ro,ii'sitifsffi D,Eed-ium dense, moist
90i 1 1"
50i3'
50/5'
60
Boring terminated at l0' 5"
6
7
I
I
t)
Project Name: Jefferson Healthcare South Campus
Project Nu mber: 2022-387 -1
Client: Jefferson Healthcare
163 5
10
t t I Boring No.: B'8
il,"\H sheet 1 or 1
c)o
o"oo
0)o
Eo
(d
c)t!
168
The Riley Group, lnc.
17522 Bothell Way NE, Bothell, WA 9801 1
Date(s) Drilled: 8131 12022 Logged By: ELW Surface Conditions: Gravel
Drilling Method(s): Hollow Stem Auger Drill Bit Size/Type: 6" auger Total Depth ol Borehole: 10.83 feet bgs
Drill Rig Type: Track Rig Drilling Contractor: Bortec Approximate
Surface Elevation:168
Groundwaler Level: Not Encountered Sampling Melhod(s): SPT Hammer Data 140 lb, 30" drop, rope and
cathead
Borehole Backtill: Bentohite Ghips Location: 834 Sheridan Street, Port Townsend, Washington
s
o
f
.oo
o)oJ
(,3
o)o
F
-qoEdCh
o
o
o_
E(d
U)
o.)oc(U
.!to0)cr
o)
o_6EBdoav
;s
o
oooE
o-oEaa()
ct)f
o)oJ
Eo-(do MATERIAL DESCRIPTION
N
S
SM
SM
Frll Brown silty SAND with trace gravel, dense, moist (Fill)
Brown silly SAND with trace gravel,moist
-oaFirtyTnnT gravel,very dense, moist (Glacial Till)with some
4
7
7
7
- Boring terminated at l0' 10"
99/10"
50/6"
50t4"
48
'153
Project Name: Jefferson Healthcare South Gampus
Project Number: 2022-387-1
Client: Jefferson Healthcare
I I I Boring No.: B-9
t "1t sneer r or r
Date(s) Drilled: 8131 12022 Logged By: ELW Surface Conditions: GraSS
Drilling Method(s): Hollow Stem Auger Drill Bit Size/Type: 6" auger Total Depth of Borehole: 10.83 feet bgs
Drill Rig Type: Track Rig Drilling Contractor: Bortec !P;";ifl;*"", rar
Groundwaler Level: Not EncoUntered Sampling Method(s): SPT Hammer Data 140 lb, 30" drop, rope and
cathead
Borehole Backfill: Bentonite Ghlps Location: 834 Sheridan Street, Pofi Townsend, Washington
o)o
o.oo
oo
tr.9
(E
o
IJJ
181
5
oo
F
-qo
Eda
o
o
o_
E(da
a)oc(d
.u)U'oE
o)
E_;E3(Bo@z
;<
o
o()oE.
o-oEa
@oal
o)oJ
.o-co-g(,MATERIAL DESCRIPTION
o)oJ
o
=
s
o5
..2o
il,sL
SM
SM -srown sitiy sANo wi-tn -rrace g-raG, mGaiifr
craysinyTnlFowi-tntriied-rau+a"i"r",rnoiiilca-ciaiTirry-
-Becomes very dense
moist
Topsoil
50/3'
50/4"
27
48
- Boring terminated at 10' 10'
10
7
7
171 10
The Riley Group, lnc.
17522 Bothell Way NE, Both€ll, WA 980i 1
166 t5
a
Project Name: Jefferson Healthcare South Campus
Project Nu mber: 2022-387 -1
Client:,fefferson Healthcare
lrIlr!
RII-EYGR()UP
Boring No.: B-10
Sheet 1 of 1
Date(s) Drilled: 8lg'l 12022 Logged By: ELW Surface Conditions: Grass
Drilling Method(s): Hollow Stem Auger Drill Bit Size/Type: 6" auger Total Depth of Borehole: 11.5 feet bgs
Drill Rig Type: Track Rig Drilling Contractor: Bortec Approximate
Surface Elevalion:175
Groundwater Level: Not Encountered 'sampling Method(s): SPT Hammer Data 140 lb, 30" drop, rope and
cathead
Borehole Backtill: Bentonite Chips Location: 834 Sheridan Street, Port Townsend, Washington
oo)
o-oo
0
c)o
co
(d
-0)IJJ
I t5
5
'165 10
o)oJ
o
=
s
o)
.tho
C',oJ
.oEo_(!.(,MATERIAL DESCRIPTION
oo
F
-go
E(!
CN
o
o
o_E(ga
0)oc(d
.9aho
CE
o)
E_bE}(s06z
be
o
oC)oE.
o-oEaaOaf
I PTiL
SM
SM SAND with trace gravel, loose to medium dense, moist
-Oay silty SAND with trace gravel, dense, moist (Glacial Till)
-Becomes very dense
-Becomes dense
Brown silly
Topsoil
11
4
6
b
Boring terminated at 1 l'6'
10
36
58
48
The Riley Group, lnc.
17522 Bothell way NE, Bothell, wA 98011
Project Name: Jefferson Healthcare South Gampus
Project Number: 2022-387 -1
Client: Jelferson Healthcare
H
Key to Log of Boring
Sheet 1 of 1
Itrlr!
RITEYGROUP
COLUMN DESCRIPTIONS
I Elevation (feet): Elevation (MSL, feet).pl Depth (feet): Depth in feet below the ground surface.
ljll Sample Type: Type of soil sample collected at the depth interval
shown.
Sample lD: Sample identification number.
Sampling Resistance, blows/ft: Number of blows to advance driven
sampler one foot (or distance shown) beyond seating interval
_ using the hammer identified on the boring log.lll Recovery (%): Core Recovery Percentage is determined based on
a ratio of the length of core sample recovered compared to the
cored interval length.
FIELD AND LABORATORY TEST ABBREVIATIONS
CHEM: Chemical tests to assess corrosivity
COMP: Compaction test
CONS: One-dimensional consolidation test
LL: Liquid Limit, percent
MATERIAL GRAPHIC SYMBOLS
Asphaltic Concrete (AC)
Bentonite chips
Portland Cement Concrete
USCS Symbol: USCS symbol of the subsurface material.
Graphic Log: Graphic depiction of the subsurface material
encountered.
MATERIAL DESCRIPTION: Description of material encountered
May include consistency, moisture, color, and other descriptive
text.
Well Log: Graphical representation of well installed upon
completion of drilling and sampling.
Moisture (%): Moisture, expressed as a water content.
Pl: Plasticity lndex, percent
SA: Sieve analysis (percent passing No. 200 Sieve)
UC: Unconfined compressive strength test, Qu, in ksl
WA: Wash sieve (percent passing No. 200 Sieve)
E
E
tr
E
ffi
ffi{
AF
Silty SAND (SM)
Poorly graded SAND (SP)
Topsoil
TYPICAL SAMPLER GRAPHIC SYMBOLS OTHER GRAPHIC SYMBOLS
PitcherSample i Waterlevel(attimeofdrilling,ATD)
2-inch-oD unlined split -j water level (after waiting)
spoon (SPT) l Minor change in material properties within aI stratum
Shelby Tube (Thin-walled, - tnferred/gradational contact between stratafixed head)? Queried contact between slrata
rl
N
E(]
n
m
IVn
Auger sampler
Bulk Sample
3-inch-OD California M
brass rings
iT "", samprer
Grab Sample
2.5-inch-OD Modified
California M brass liners
GENERAL NOTES
1: Soil classilications are based on the UniJied Soil Classification System. Descriptions and slratum lines are interpretive, and actual lithologic changes may begradual. Field descriptions may have been modified to reflect results of lab tests.2: Descriptions on these logs apply only at the specilic boring localions and at the time the borings were advanced. They are not warranted to be representativeoI subsurface conditions at other locations or times.
The Rll6y croup, lnc.
17522 Bothell Way NE, Bothelt, WA 9g0i 1
oo
c.9
(E
o
IJJ
o)o,
o-oo
oo
FoaEda
o
_9o.E(!
U)
atoc(U
.aah(lttr
o)
o.dE}doav
Eto
ooc)E.
o-oEaaoU)f
o)3
.o
o-(U
o MATERIAL DESCRIPTION
t')oJ
c)
ts
s
(1)
l
..2o
ITHE RILEY GROUP, INC.
17522 BothellWay NE
Bothell, WA 98011
1
PHoNE: (425) 41s-0551
FAX: (425) 41s-0311
GRAIN SIZE ANALYSIS
ASTM D421 DLL O,D2487, D6913
B-1efferson Healthcare South
20'2022-387-L
EW sl6l2022
SAMPTE IDITYPE
SAMPLE DEPTH
DATE RECEIVEDDATE
PROJECT TITTE
PROJECT NO.
570.564r.2
15.9570.5
554.5
Weight Of Sample (gm)
Tare Weight (gm)
Total15.9
70.7
554.6
13
WATER CONTENT (Delivered Moisture)
Wt Wet Soil & Tare (gm) (w1)
Wt Dry Soil & Tare (gm) (w2)
Weight of Tare (gm) (w3)
Weight of Water (gm) (w4=w1-w2)
Weight of Dry Soil (gm) (w5=w2-w3)
Moisture Content 100 Wt Ret
SIEVE ANATYSIS
Cumulative
(Wt-Tare) (%Retained)% PASS
% COBBLES
% C GRAVEL
% F GRAVEL
% C SAND
% M SAND
% F SAND
% FINES
%TOTAL
0.0
0.0
6.4
5.5
4?.4
28.3
16.3
100.0
L2.0"cobbles
coarse gravel
coarse gravel
coarse gravel
coarse gravel
coarse gravel
fine gravel
fine gravel
2.5"
1.5"
1.0"
o.75"
0.50"
0.375"
#4
#10
#20
#40
#60
#100
#200
PAN
ne gravel
D10 (mm)
D30 (mm)
D60 (mm)
Cu
Cc
a.27
0.58
4.3
27.4
o.4
sand
medium sand
medium sand
ne sand
ne sand
sand
silt/clay
12"3' 2' '1" .75" .375" #4 #10 #20 #40 #60 #100 #200
%
P
A
s
s
I
N
G
100
90
80
70
60
50
40
30
20
10
0
1000 100 10 7 0.1 0.01 0.001
Grain size in millimeters
DESCRIPTION
uscs
Prepared For:Reviewed By:
ELW
0.00 100.0015.9 0.00
100.000.00 0.0015.9
100.000.00 0.0015.9
100.000.00 0.0015.9
96.9716.80 3.0332.7
93.5835.60 6.4251.5
87.9966.60 72.0182.5
44.63307.10 55.37323.O
20.r2443.00 79.88458.9
16.34464.00 83.66479.9
0.00554.60 100.00570.5
SAND with trace gravel
SM
Healthcare
trIlrI
RILEYGR(}UP
THE RITEY GROUP, INC.
17522 BothellWay NE
Bothell, WA 98011
PHoNE: (425) 415-0551
FAX: (425) 41s-0311
D2487 D6913
GRAIN SIZE ANALYSIS
ASTM D42L, D422,
Healthcare South B-2
2022-387-1,2.5'
EW 91612022 813U2o22
SAMPTE |D/TYPE
SAMPTE DEPTH
DATE RECEIVEDDATE
PROJECT TITTE
PROJECT NO.
589.6 540.1
540.1"15.9
15.9
Weight Of Sample (gm)
Tare Weight (gm)
Total 524.2
49.5
524.2
WATER CONTENT lDelivered Moisturel
Wt Wet Soil & Tare (gm) (w1)
Wt Dry Soil & Tare (gm) (w2)
Weight of Tare (gm) (w3)
Weight of Water (gm) (w4=w1-w2)
Weight of Dry Soil (gm) (w5=w2-w3)
Moisture Content 100 9 Wt Ret
SIEVE ANATYSIS
Cumulative
(Wt-Tare) (%Retained)% PASS
% COBBLES
% C GRAVET
% F GRAVEL
% C SAND
% M SAND
% F SAND
% FINES
%TOTAL
0.0
3.9
8.8
4.2
24.2
32.8
22.1,
100.0
12.o"
3.0"
2.5u
2.O"
1.5"
cobbles
coarse gravel
gravel
0.75"
0.50"
0.375"
coarse gravel
coarse gravel
coarse gravel
fine gravel
fine gravel
fine gravel
coarse sand
medium sand
medium sand
D10 (mm)
D30 (mm)
D60 (mm)
Cu
Cc
o.21
0.58
4.5
27.4
o.4
#10
#20
#40
#50
sand
ne sand
PAN
fine sand
fines
silt/clay
12"3' 2' '1..75' .375' #4 #1 o #20 #40 #60 #100 #200
%
P
A
s
s
I
N
G
100
90
80
70
50
50
40
30
20
10
0
I
G\
1000 100 10 1 0.1 0.01 0.001
Grain size in millimeters
DESCRIPTION
uscs
Prepared For:Reviewed By:
ELW
15.9 0.00 0.00 100.00
15.9 0.00 0.00 100.00
15.9 0.00 0.00 100.00
36.6 20.70 3.95 96.05
58.6 42.70 8.15 91.85
82.6 66.70 L2.72 87.28
r.04.5 88.60 15.90 83.10
252.4 236.50 45.t2 54.88
394.2 378.30 72.t7 27.83
424.2 408.30 77.89 22.17
540.1 524.20 100.00 0.00
Silty SAND with trace gravel
SM
Hedlthcore
ltIlrr
RILEYGRt}UP