HomeMy WebLinkAbout3189 Adopting the Capital Improvement Plan 2018-2023Ordinance 3189
Page 1 of 2
Ordinance No. 3189
AN ORDINANCE OF THE CITY OF PORT TOWNSEND, WASHINGTON,
ADOPTING THE CAPITAL IMPROVEMENT PLAN FOR 2018 THROUGH 2O23
WHEREAS, the City of Port Townsend has adopted a Comprehensive Plan and has
amended it in accordance with the requirements of the Growth Management Act ("GMA")
(Chapter 36.70A of the Revised Code of Washington); and,
WHEREAS, the GMA requires a capital facilities plan as a mandatory element of the
City's Comprehensive Plan and the City has adopted such a plan, commonly referred to as the
City's Capital Improvement Plan; and,
WHEREAS, the Capital Improvement Plan provides the six -year capital facility program
for the City, subject to appropriation by the Council of funding for the projects contained in the
Plan; and,
WHEREAS, RCW 36.70A.130 and Section 20.04.030A(7) of the Port Townsend
Municipal Code allow the city to adopt changes to the Capital Improvement Plan concurrently
with the adoption of the city's budget; and,
WHEREAS, the City Council held a public hearing on November 6, 2017, on the
proposed 2018-2023 Capital Improvement Plan.
NOW THEREFORE, the City Council of the City of Port Townsend do ordain as
follows:
Section 1. Findings _ lid .Conclusions, The proposed 2018-2023 Capital Improvement
Plan is consistent with and implements the currently -adopted Capital Facilities and
Utility Elements of the Comprehensive Plan are consistent with RCW 36.70A.070(3) and
the Comprehensive Plan, and are in the public interest.
Section2. The City adopts the 2018-2023 Capital Improvement Plan as substantially
shown at Exhibit A.
Section 3 eye'rability. If any sentence, clause or phrase of this Ordinance should be
held to be invalid or unconstitutional by a court of competent jurisdiction, such invalidity
or unconstitutionality shall not affect the validity or constitutionality of any other section,
sentence, clause, or phrase or work of this ordinance.
Section 4. 1"ransmittal to Department of Commerce. The City Clerk shall transmit a copy
of this Ordinance to the State Department of Commerce (DOC) within ten (10) days of
adoption of this ordinance.
Ordinance 3189
Page 2 of 2
Section 5. Effective Date. This Ordinance shall take effect and be in force 5 days
following its publication in the manner provided by law.
ADOPTED by the City Council of the City of Port Townsend, Washington, at a regular
meeting thereof, held this 6th day of November, 2017.
Deborah S. Stin,, ot)
Mayor
Attest: Approved as to Form:
Joanna Sanders, MMC
City Clerk
Steven L. Gross
City Attorney
Ordinance 3189 Exhibit A
Project
0095
0096
0102
Page I of 14
Capital Improvement Plan 2018 - 2023
General Government
This plan shows the 6-year plan for capital projects.
2018 2018 2018
2019
2020 2021 2022 2023 6-Year Total
Prelirninary Adopted Revised
Mountain View Phase III
Voted Bond
Funding Sources
Voted Bond
1,040,000
1,040,000
Total
1,040,000 -
1,040,000
Expenditures
-
Design/Construction
1,000,000
1,000, 000
Project Management
40,000
40,000
Total
1,040,000
-
1,040,000
Mountain View CDBG
Funding Sources
CDBG
350,000
350,000
Total
350,000 _
_
_ 350,000
Expenditures
Design/Construction
330,000
330,000
Project ,VaaaageTnent
20,000
20,000
Total
350,000
350,000
Library
Funding Sources
2017 Bond
250,000
250,000
Gen Gov CIP Fund Balance
25,000
25,000
Donation
74,500
74,500
Total
349,500 = -
349,500
Expenditures
-
Design/Construction
329,500
329,500
Project Management
20,000
20,000
Total
349,500
349,500
11/1/2017 Page 1 of 14 Pages
Ordinance 3189 Exhibit A
Page 2 of 14
Capital Improvement Plan 2018 - 2023
Street
This plan shows the 6-year plan for capital projects.
2018
2018 2018 2019 2020 2021
2022 2023 6-Year Total
Project
Preliminary
Adopted Revised
1058
Howard St
Funding Sources
CERB
300,000
300,000
REET2
5,000
5,000
Total
305,000
305,000
Expenditures
-
Construction
-
Project Management
10,000
10.000
Total
10,000
m
10,000
1106
Water St Overlay - Taylor to Ferry Terminal
Funding Sources
-
TIB
600,000
600,000
2017 Bond
760,000
760,000
Total
1,360,000
1,360,000
Expenditures
-
Construction
1,260,000
1,260,000
Project Management
100,000
100,000
1,360,000
1,360,000
1067
Jefferson St
Funding Sources
-
Bond
233,000
233,000
TIB
375,000
375,000
Total
608,000
608,000
Expenditures
-
Design
100,000
100,000
Construction
468,000
468,000
Project Management
40,000
40,000
Total
608,000
608,000
11/1/2017 Page 2 of 14 Pages
Project
1008
1145
1009
Ordinance 3189 Exhibit A
Page 3 of 14
Capital Improvement Plan 2018 - 2023
Street
This plan shows the 6-year plan for capital projects.
2018 2018 2018
2019 2020 2021
2022 2023 6-Year Total
Preliminary Adopted Revised
Visitor Center Sims Way Frontage
Funding Sources
LTAC
-
2017 Bond
624,813
624,813
Street CIP Fund Balance
10-187
10,187
Total
635,000
635,000
Expenditures
-
Design
60,000
60,000
Construction
523,000
523,000
Project Managerne nt
52.000
52,000
Total
635,000
635,000
SR 20 Pedestrian Walkway - Logan to Hancock
Funding Sources
-
Unsecured
1,000,000
1,000,000
TAP
70,000
70,000
2017 Bond
20,000
20,000
Total
90,000
1,000,000
1,090,000
Expenditures
-
Design
65,000
65,000
Construction
900,000
900,000
ProjW, Managernem
15,000
100,000
115.000
80,000
1,000,000
= 1,080,000
Complete Sts (TIB)
Funding Sources
Note: $2S0,000 Grant Funds received in 2017
TIB
-
BEET
25,000
25,000
Total
25,000
25,000
Expenditures
-
Construction
250,000
250,000
Project Management
25M0
25,000
275,000
275.000
11/1/2017 Page 3 of 14 Pages
Project
1047
1146
Unfunt
1117
Ordinance 3189 Exhibit A
Page 4 of 14
Capital Improvement Plan 2018 - 2023
Street
This plan shows the 6-year plan for capital projects.
2018 2018 2018
2019 2020 2021
2022 2023 6-Year Total
Preliminary Adopted Revised
7th St Preliminary Design
Howard to Discovery Rd
Funding Sources
2017 Bond
5,000
5,000
Total
5,000
5,000
Expenditures
-
Design
3,000
3,000
Construction
Project ManaEernent
Z000
2,000
Total
5,000
5.000
SR20 Overlay
Funding Sources
REET
5,000
5,000
Total
5,000
5,000
Expenditures
-
Construction
-
Project Manage men,
5,000
5,000
Total
5,000
5,000
led:
PUD Undergrounding/Pathways
Funding Sources
-
Unfunded
Total
Expenditures
Construction
Project Managernent
Total
11/1/2017 Page 4 of. 14 Pages
Project
Ordinance 3189 Exhibit A
Page 5 of 14
Capital Improvement Plan 2018 - 2023
Street
s This plan shows the 6-year plan for capital projects.
2018 2018 2018
2019 2020
2021
2022
2023
6-Year Total
Preliminary Adopted Revised
Discovery Road I Sheridan to Howard St
Funding Sources
Unsecured
770,000
7,580,000
8,350,000
Total
770,000 7,580,000
8,350,000
Expenditures
-
Design
700,000
700,000
Construction
7,500,000
7,500,000
Project Management
70,000
80,000
150.000
Total
-
770,000
7,580,000
8,350,000
Washington St Downtown Streetscape
Funding Sources
-
Unsecured Funds
350,000
2,000,000
2,350,000
-
350,000
2,000,000
2,350.000
Total
Expenditures
-
Design
350,000
350,000
Construction
2,000,000
2,000,000
Total
-
350,000
2,000,000
2,350,000
Sims Way Improvements II
Funding Sources
WSDOT - Unsecured
600,000
4,000,000
4,600,000
Other Unsecured Funds
150,000
1,000,000
1,150,000
Total
750,000
5,000,000
5,750,000
Expenditures
-
Design
750,000
750,000
Construction
5,000,000
5,000,000
Total
- -
750,000
5,000,000
5,750,000
11/1/2017 Page 5 of 14 Pages
Project
DIM
1108
Ordinance 3189 Exhibit A
Page 6 of 14
Capital Improvement Plan 2018 - 2023
Street
* This plan shows the 6-year plan for capital projects.
2018 2018 2018
2019
2020
2021
2022
2023
6-Year Total
Preliminaq Adcipted Revised
Sidewalk Project - ADA
Funding Sources
Unsecured
50,000
50,000
50,000
50,000
50,000
250,000
Total a
50,000
50,000
50,000
50,000
50,000
250,000
Expenditures
-
Construction
50,000
50,000
50,000
50,000
50,000
250,000
Project Maria e e fit.
-
Total -
50,000
50,000
50,000
50,000
50,000
250,00
Rainier St Extension
Funding Sources
-
NOW: conceptual uesign in [ui
-
Unsecured
-
Total -
-
-
-
Expenditures
_
Construction
-
Protect l ana ernent
=
Total
-
e
Non -Motorized AB17-009
Funding Sources
_
Unfunded
-
Total
Expenditures
Construction
_
Project' araagernert
n
Total
11/1/2017 Page 6 of 14 Pages
Ordinance 3189 Exhibit A
Page 7 of 14
Capital Improvement Plan 2018 - 2023
Water
This plan shows the 6-year plan for capital projects.
2018 2018 2018 2019 2020 2021 2022 2023 6-Year Total
Project Preliminary Adopted Revised
6046 Water Street Overlay
Funding Sources
System Development Charges 900,000 900,000
2017 Utility Revenue Bond -
Total 900,000 - - - - - 900,000
Expenditures
Design/Construction 810,000
Project Management 90,000
810,000
90,000
Total 900,000 - - 900,000
6041 Big Quill Diversion 0
Funding Sources
OGWS 669,500
Port Townsend Paper Company 669,500
Total 1,339,000
Expenditures
669,500
669,500
1,339.000
Design/Construction 1,180,000 1,180,000
Proiect Management 120.000 120,000
Total 1,300,000 - - - - - 1,300,000
11/1/2017 Page 7 of 14 Pages
Ordinance 3189 Exhibit A
Page 8 of 14
Capital Improvement Plan 2018 - 2023
Water
* This plan shows the 6-year plan for capital projects
2018 2018 2018 2019 2020 2021 2022 2023 6-Year Total
Project Preliminary Adopted Revised
6017 5MG Reservoir
Note: ror expenditures in 201/
Funding Sources -
DWSRF 812,477 812,477
PWTF 903,621 903,621
City Match - -
Total 1,716,098 - 1,716,098
Expenditures -
Total
6161 LT2
Note: nor expenditures in i01/
—
Funding Sources
_
DWSRF
1,893,666
1,893,666
Operating Transfer
750,000
750,000
Total 2,643,666 -
_ _ -_ 2,643.666
Expenditures
-
Design/Construction
1,818,000
1,818,000
Project Management
50,000
50,000
Total 1,868,000 z
a 1,868,000
Ongoing 6000 Water General
Funding Sources
Water Capital Surcharge
160,000
160.000
160.000
160,000
160,000
800,000
Total -
-- 160,000
160,000
160,000
160,000
160,000
800,000
Expenditures
-
Design/Construction
160,000
160,000
160,000
160,000
160,000
800,000
Total -
160,000
160,000
160,000
160,000
160,000
800.000
11/1/2017 Page 8 of 14 Pages
Project
7046
7001
7013
Ordinance 3189 Exhibit A
Page 9 of 14
Capital Improvement Plan 2018 - 2023
Sewer
This plan shows the 6-year plan for capital projects.
2018 2018 2018
2019
2020
:20-271
2422
2023 6-YearTotal
Preliminary Adopted Revised
Water Street Overlay
Funding Sources
-
Development Charges
80,000
80,000
-systern
Total
80,000
80,000
Expenditures
-
Design/Construction
60,000
60,000
Project Management
20,000
20,000
Total
80,000
80,000
Collection System Improvements
-
Funding Sources
-
Sewer Capital Sureharge
160,00D
160,000
160,000
160,000
640,000
Total
160,000
160,000
160,000
160,000
640,000
Expenditures
-
Design/Construction
160,000
160,000
160,000
160,000
640,000
Project Management
-
Total
160.000
160,000
160,000
160,000
640,000
Cluffall Replacement
-
Infrastructure Condition
Funding Sources
-
CCWF Loan/Grant
200,000
200.000
400,000
System Development Charges
100,000
100,000
200,000
Unfunded
400 00
4,000,000
4,400,000
Total
300,000
300,000
400,000
4,000,000
5,000,000
Expenditures
-
Design
225,000
250,000
350,000
825,000
Construction
3,700,000
3,700,000
Project Management
75,000
50.000
50,000
300,000
475,000
Total
300,000
300,000
400,000
4,000,000
5,000,000
11/1/2017 Page 9 of 14 Pages
Project
Unfunc
7018
Ordinance 3189 Exhibit A
Page 10 of 14
Capital Improvement Plan 2018 - 2023
Sewer
* This plan shows the 6-year plan for capital projects.
2018 ?01 2018
2019 2420 2021;
20222 2 t2
6-Year Total
Preliminary Adopted Revised
ed
South West Sewer Pump Station
Contributes to Economic Development
Funding Sources
-
Unsecured - Loans, Grants, LID
4,330,000
4,330,000
Total -
4,330,000
4,330,000
Expenditures
Design/Construction
4,000,000
4,000,000
Project Management
330,000
330,000
Total
-
4,330,000
4,330,000
7026 Gaines Street Pump Station
Infrastructure Condition Mandate (Vulnerability)
Funding Sources
Unsecured - FEMA - potential funding source
Total
Expenditures
Design/Construction
Project Management
" Shoreline Stabilization -Not Currently Funded
465,000 465.000
- -
- - 465,000 465,000
380,000 380,000
85,000 85,000
Total - 465,000 465,000
11/1/2017 Page 10 of 14 Pages
Ordinance 3189 Exhibit A
Project
7014
7004
Page 11 of 14
Capital Improvement Plan 2018 - 2023
Sewer
* This plan shows the 6-year plan for capital projects.
201 2018 2018
-:
2,419
2020 2021>
2,0 2
2023; 6-Year Total
prel minary Adopted... Revised
Infiltration/inflow Removal
Desirable Investment in System
Funding Sources
Unfunded
20,000
260,000
Total - -
260,000
260.000
Expenditures
-
Design/Construction
200,000
200,000
Project Management
60,000
60,000
Total -
260,000
260,000
Wastewater Master Plan/WWTP
-
Funding Sources
-
Capitai Surcharge
130,000
130,000
Total - -
130,000 -
130,000
Expenditures
-
Design/Construction
100,000
100,000
Project Management
30,000
30,000
Total --
130,000
-
- 130.000
11/1/2017 Page 11 of 14 Pages
Project
8001
8046
8028
Capital Improvement Plan 2018 - 2023
Storm
* This plan shows the 6-year plan for capital projects.
2018 2018 2018
2019
2020 2021 2022 2022 6-Year Total
Preliminary Adopted Revised
Stormwater Management Plan
Funding Sources
_
Capital Surcharge
Storm Fund
60,000
Total
60,000
-
_ - 60,000
Expenditures
-
Design/Construction
30,000
30,000
Project Management
30,000
30,000
Total
60,000
- 60,000
Water Street Overlati
s
Funding Sources
-
Capiital Surcha ee
100,000
100,000
Total
100,000
s 100,000
Expenditures
Design/Construction
20,000
20,000
Project Management
100,000
100.000
Total
120,000
120.000
CERB Regional Facility
Funding Sources
-
CERB
850,000
Capital Surcharge
5U*O
50.000
Total
900,000
-
- - 900,000
Expenditures
-
Design/Construction
750,000
750,000
Project Management
50,000
50.000
Total
800,000
_
800.000
11/1/2017 Page 12 of 14 Pages
Project
8022 Logan Street
Funding Sources
apical Surcharge
Expenditures
Design/Construction
Project Management
Capital Improvement Plan 2018 - 2023
Storm
* This plan shows the 6-year plan for capital projects.
2018 2018 2018 2019 2020 2021
Prefiminary Adopted Revised
10,000
Total 10,000 - -
15,000
5,000
Total 20,000
Ordinance 3189 Exhibit A
Page 13 of 14
2022 2022 6-Year Total
10,000
10,000
15,000
5,000
20,000
11/1/2017 Page 13 of 14 Pages
Ordinance 3189 Exhibit A
Page 14 of 14
Capital Improvement Plan 2018 - 2023
General Government
` This plan shows the 6-year plan for capital projects.
1 31
2018 2018 2019 2020
2021
2022
2023 6-Year Total
General Government
Funding Sources
Preliminary
Adopted Revised
CDBG
350,000
- -
350,000
Heritage Grant
- - -
-
- -
Donation
74,500
-
- 74,500
Voted Bond
1,290,000
-
-
1,290,000
2017 Utility Revenue Bond
Fund Balance
25,000
ioi
i i u im. W��V
V
III i uIViM
Expenditures
Design/Construction
1,659,500
-
-
1,659,500
Project Management
80,000
-
-
80,000
Street
Funding Sources
WSDOT -STP funds
- -
600,000
4,000,000 4,600,000
TAP
70,000
-
-
70,000
TIB
975,000
-
975,000
Local Funds
-
2017 Bond
1,642,813
- - -
-
1,642,813
CERB
300,000
300,000
BEET
35,000
-
-
- 35,000
Fund Balance
10,187
-
-
- 10,197
Unfunded
5o'000 '050,000
gill w a emu
1,170,„000
m mmd
917801WO
m we°I mum
1„050,000 13,100,000
m.0 aura a uum
Expenditures
Design/Construction
228,000
- - -
1,050,000
750,000
- 2,028,000
Construction
2,501,000
- 50,000 950,000
50,000
9,550,000
5,050,000 18,151,000
ProNve1:6'lutna gemant
249,000
- '100,00o
70,000
80,000
499,000
d
m
'mj�uju.
'd .0 rowm
mi mmm m,oui.imaw
Water
Funding Sources
Capital Surcharge
.. 160,000 1.60,000 160,000 1.60,000 160,000 800,000
DWSRF
2,706,143 ••
2,706,143
PWTF
903,621
-. - 903,621
Operating Transfer
750,000
- - - 750,000
2017 Utility Revenue Bond•
SDC
900,000
- - - 900,000
OGWS
669,500 -
- - - 669,500
Other - PTPC
669„5�00
_ -. 669,5
IIIIIIIIIIIIIIIIII��p�p��������p�p��������
An8MdM8NM1lry�lli
m wmm a mmm i
Expenditures
Design/Construction
3,808,000-
160,000 160,000 160,000 160,000 160,000 4,608,000
Project Management
260,000
•-- •- 260,000
Sewer
Funding Sources
Capital Surcharge ••
- 160,000 290,000 160,000 160,000 - 770,000
Sewer Transfer SDC 180,000 -
100,000 - - •• 260,000
CCWF Loan/Grant 200,000
200,000 - - ^• - 400,000
Revenue Bond-••
- -
Unsecured Funds -
400,000 4,000,000 260,000 4,795,000 9,455,000
LID
Expenditures
Design/Construction 285,000 410,000 610,000 3,860,000 360,000 4,380,000 9,905,000
Project Management 95,000 - - 50,000 80,000 300,000 60,000 415,000 1,000,000
Storm
Funding Sources
CERB 850,000 850,000
Storm Fund 60,000 - - - - 60,000
Capuud Surcharge 160,000 - 160,000
Expenditures
Design/Construction 815,000 - - -_ 815,000
Projlvuc M44wgemern.t 185,000 - - - - 185,000
i. _lolm7i. a... m�I'u wmm_. �mm
11/1/2017