Loading...
HomeMy WebLinkAbout13-016 Authorizing City Manager to Award and Sign all Contracts for Construction of Waterfront Esplanade Project Final Phase Resolution 13-016 Waterfront Esplanade Project Page 1 of 2 RESOLUTION NO. 13-016 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF PORT TOWNSEND, WASHINGTON AUTHORIZING THE CITY MANAGER TO AWARD AND SIGN ALL CONTRACTS FOR THE CONSTRUCTION OF THE WATERFRONT ESPLANADE PROJECT, FINAL PHASE WHEREAS, in July 2008 the City of Port Townsend acquired the 2008 Council Bond for specific projects in the Historic Downtown area; and WHEREAS, the Waterfront Esplanade Project, Final Phase is the final downtown project envisioned in the 2008 Council Bond, implementing the waterfront improvements as designated in the East Downtown Streetscape Plan; and WHEREAS, the Madison Street Improvements Project provided an opportunity to complete a portion of the Waterfront Esplanade Projects in conjunction with that project; and WHEREAS, during Phase 1 the City of Port Townsend completed the demolition and fill of the Tidal Clock; reinforcement of the seawall between City Dock and the Quincy Street Dock; and removal of the old dock that was adjacent to the old ferry ramp; and WHEREAS, during Phase 2 the City of Port Townsend completed the improvements of the waterfront area between the Pope Marine Building and Quincy Street; and WHEREAS, January 22, 2013, the City received a PIF Grant from Jefferson County allowing for completion of the Esplanade; and WHEREAS, on April 11, 2013, the City opened the bids for the construction of the Esplanade- Final Phase and HB Hansen Construction of Lynden, Washington was the apparent low bidder for the construction project; and WHEREAS, staff has reviewed the bid tabulations has checked references and recommends award of the project to HB Hansen Construction of Lynden, Washington; and WHEREAS, it is the desire of the City Council to move forward with this project construction in the most expedient manner; and NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Port Townsend as follows: The City Council of Port Townsend authorizes the City Manager to award and sign all contracts for construction of Waterfront Esplanade Project, Final Phase. Resolution 13-016 Waterfront Esplanade Project Page 2 of 2 ADOPTED by the City Council of the City of Port Townsend at a regular meeting thereof, held this 22nd day of April 2013. David King, Mayo Attest: Approved as to form: Pamela Kolacy, MMC John Watts City Clerk City Attorney