From Mayor David King - IT’S TIME TO DECIDE ABOUT THE LIBRARY –
April 8 Open House on Library Options
In my boatbuilding and repair business a boat “refit” project is not the same as a
repair. A major refit will include improvements like hull extensions, new engines,
and interior remodeling as well as repair of existing systems and structure. The
City Library and Carnegie “campus” are undergoing a major refit. The repair com-
ponents of the refit include the seismic retrofit of the original Carnegie building and replacement
of the retaining walls and fractured concrete stairways. The planned improvements include resto-
ration of the Pink House, recently completed, and as originally envisioned and planned over the
last several years the replacement of the current single-story extension with a new two-story plus
basement addition.
Design and approval of the new addition (called “Phase 5” of the project) was the result of an ex-
tended public process that included evaluation of the current uses of the Library, the constraints
imposed on those uses by the current facility, and a projection of the growth of those uses over
time to arrive at a library campus suitable for the community’s “Next Hundred Years.”
The expanded library facility did not envision uses other than those for which the community had
already demonstrated an appetite by making our Library one of the busiest in the state. But en-
thusiastic support for the library, plus an optimistic plan for funding, resulted in an ideal design
largely uncompromised by constraints other than the size of the site.
The plan to pay for it reflected that idealism. Of the $7.75 million cost of the expansion and repair
of the failing walkways and retaining walls, $4 -5 million were to be raised by the City and the Li-
brary Foundation working together to secure grants and private donations. The up to $3 million
remaining was to be provided through a Council-approved or a voter-approved bond and only
after at least 80% of the rest of the funding was secured.
But it was not to be. To date the Foundation has raised about $1.2 million towards Phase 5 from
a combination of private donations and grants and a portion of that requires matching funds. The
City has provided $450 thousand from councilmanic bond funds for the design of expansion pro-
ject. There are still repair components of the refit that need to be funded so there is no option that
will not require further investment of public funds in the property. Completion of the library “refit”
project that includes significant improvements beyond the renovation of the Pink House and seis-
mic retrofit of the Carnegie building will require a voted bond. But at a minimum we are faced
with some level of expense to get our Library back into the Carnegie Campus and operational.
Absent some level of bond support these expenses would result in a library functioning at a re-
duced level of service and capacity.
A Council-approved bond (paid for out of existing revenues) is not practical now because City
finances to repay a bond are limited and the additional bond debt might exceed our statutory limit
in the event of devaluation of the City’s assessed value. A voter-approved bond is the only option
at this point. Council could place a bond measure equal to the majority of the original project cost
before the voters but has determined that public consideration of an array of options and their
impact on the services we want from our library should precede a thumbs up or down ballot
measure based solely on cost.
On March 18, after working with the Library Foundation for several weeks, Council adopted a
process to “re-set” the library expansion project given these changed circumstances. On April 8,
there will be an open house at the Carnegie Library for the public to review and provide comment
on Library options.
HPDLOFLW\FRXQFLO#FLW\RISWXVZZZFLW\RISWXV$SULO
For the town meeting the City has prepared five alternatives ranging from limited improve-
ments to the Carnegie building only, to the full two-story and basement implementation of
Phase 5. General cost and capacity information is included with each scenario. These docu-
ments are available in hard copy at City Hall and at the Library or online at the City’s website
or here [link] if you’re reading this online. Please review the options presented in these docu-
ments and come to the meeting on the 8th to give us your thoughts. If you cannot attend the
meeting on the 8th please mail us your comments (write “Library Project” on the envelope) or
drop them by the Library or City Hall. Council plans to take action on April 29 that would des-
ignate the preferred alternative and amount of voter-approved bond.
By approving a voted bond we would guarantee payment through our property taxes. This
does not necessarily mean that the bond has to be paid by property taxes. The City could
apply other funds to the bond including monies raised by the continuing efforts of the City
and the Library Foundation. The bond costs cannot be precisely known until they are sold
but assuming property tax covered the entire debt-service the estimated 20-year annual cost
on the property tax bill of a house with a $300,000 assessed value would be:
Everyone loves the library. Even critics of the current expansion plan preface their criticism
with affection for the institution. If we had raised the $4 - 5 million from other sources as origi-
nally planned I’d be a vocal supporter of bonding for the balance of the expansion as we’d
planned to do in 2010. But the changed circumstances for funding the project warrant review
of the project by those who will have to pay for it. We can have the library expansion as de-
signed if we are willing as taxpayers to bear the cost. Or we can revise the scope of the pro-
ject and have a more modest result at a lower cost. Council has the responsibility for what-
ever measure is placed before the voters and has instituted this process to help craft a
measure that will be broadly supported. Voters will retain the final say.
Bond Amount
Annual Property Tax for
$300,000 Home
6,000,000$ $113.40
5,000,000$ $94.50
4,000,000$ $75.60
3,000,000$ $56.70
2,000,000$ $37.80
Bond Amount
Annual Property Tax for
$300,000 Home
6,000,000$ $113.40
5,000,000$ $94.50
4,000,000$ $75.60
3,000,000$ $56.70
2,000,000$ $37.80
PORT TOWNSEND PUBLIC LIBRARY EXPANSION ALTERNATIVES
(Note: These alternatives are conceptual in nature and not intended to reflect a specific design.)
Current Carnegie and 1990
Addition Library Space Alternative #1 Alternative #2 Alternative #3 Alternative #4 Alternative #5 Alternative #6
Public Space
Entry & Display Areas (80
Adult Collections (2265 SF)
Adult Reading Areas (500SF)
Study Room (400 SF)
Computers (140SF) Children's Area (1265 SF)
Young Adult Area (50 SF)
Staff & Support Services
Mechanical Spaces
Storage
Toilets
Building Circulation
Building Construction
Total
4700 SF
1095 SF
110 SF
90 SF
275 SF
390 SF
1630 SF
8290 SF
?
Funding Available
The following funding is available for Library
construction (subject to Library Foundation
approval and meeting NEH grant conditions):
Heritage Capital Project Fund $0.1 M
NEH Grant $0.5 M
Philanthropic Gifts and Pledges $0.7 M
Total: $1.3 M
Description:
The library moves back into the current
building as-is. The only work scope
includes setting up shelving and
furniture for occupancy.
Optional construction: Paint, re-carpet,
and minimal operational modifications
(counters, work spaces, etc.)
Description:
Construction scope includes functional
upgrades such as elevator
replacement, mechanical equipment
replacement, south site restoration &
parking lot improvements.
Description:
Construction scope includes a 2,000
SF, one story addition to the existing
footprint and functional upgrades such
as elevator replacement, mechanical
equipment replacement, south site
restoration and parking lot
improvements. This alternative will
provide additional space for collections.
Description: Construction scope includes a 9,200
SF, two story addition to the existing
Carnegie, Carnegie library restoration,
new mechanical systems, south site
restoration & parking lot improvements.
The alternative will provide additional
space for collections & will provide the
necessary infrastructure to build an
additional 5,600 SF, two story addition
in the future.
Description: Construction scope includes a 14,700
SF, two story + basement addition to
the existing Carnegie, Carnegie library
restoration, new mechanical systems,
south site restoration and parking lot improvements. The alternative meets
current & near-future space needs, &
maintains the size of both existing
parking lots.
Library Building Size:
8,290 SF
Library Building Size:
8,290 SF
Library Building Size:
10,290 SF
Library Building Size:
13,960 SF
Library Building Size:
19,372 SF
Construction Cost: $20K - $180K
Other Costs:
Total Cost: $20K - $180K
Construction Cost: $1.3 - $1.5 million
Other Costs: $750K
Total Cost: $2.0 – $2.2 million
Construction Cost:$1.8 –$2.0 million
Other Costs: $1 million
Total Cost: $2.8 – $3.0 million
Construction Cost:$3.5-$3.75 million
Other Costs: $2 million
Total Cost: $5.5 - $5.7 million
Construction Cost:$5.0-$5.25 million
Other Costs: $2.5 million
Total Cost: $7.5 – $7.75 million
Bond Costs
The bond costs cannot be precisely known
until they are sold but assuming property tax
covered the entire debt-service the estimated
20-year annual cost on the property tax bill of
a house with a $300,000 assessed value
would be:
Bond Amount
Annual Property Tax for
$300,000 Home
6,000,000$ $113.40
5,000,000$ $94.50
4,000,000$ $75.60
3,000,000$ $56.70
2,000,000$ $37.80
Library Construction to Date
Pink House Restoration (2011) - $134K
PT Library Foundation - $134K
Carnegie Seismic Retrofit (2012) - $611K
FEMA - $448K; City Bond - $163K
Carnegie Building Repairs (2012) - $215K
WA State Heritage Capital Grant - $215K
Library Design Process (2006-11) - $446K
City Bond - $446K
Issues:x No expansion.
x Shortest Timeline
x Least expensive option
x Reduced collection space due to
limitations in Carnegie results in
2/3 of collection in storage
Interior of Carnegie not fully
restored
x Operational “friction” between
different users sharing common
spaces (reading / computer / kids / adults) x Not a true no cost option
x Building systems will still need to
be upgraded (HVAC, restroom,
etc.)x Space and operation issues that
faced library still present
x Doesn’t address library growth
Issues:x No expansion
x Outdoor site and parking
improvements
x Existing building systems
upgraded (HVAC, restrooms,
elevator)
x Least expensive operating costs
x Reduced collection space due to
limitations in Carnegie results in
2/3 collection in storage
Interior of Carnegie not fully
restoredx Operational “friction” between
different users sharing common
spaces (reading / computer / kids /
adults)
x Space and operation issues that
faced library still present
x Doesn’t address library growth
Issues:x Provides more space (2000sq.ft.)
x Need to functionally reprogram
library uses (may not be
operationally efficient or user
friendly) x 1/3 of adult and 1/3 of children’s
collections in storage x Keeps existing addition
x Building system upgraded and/or
replaced (more comprehensive
than Alt. #2)
x Does not lend itself to future
expansion (building systems &
space configuration) x Increased operating cost
x Meets some of original project
goals – no distinct young adult
space; children’s area limited
x Carnegie interior not fully restored
(elevator and restrooms remain)
Issues:x Provides 2/3 increase in library
space, (completes children’s area) x Supported by Foundation
x Increase operating cost
x Would be more operationally
efficient and user friendly; Reduces
operational friction between uses
x Cost - even with the NEH Grant
and other funds raised, the
community would pay the majority
of project costs x Meets many of original project
goals
x Interior restoration of Carnegie
x Lends itself to future
x Building systems upgraded and/or
replaced (more comprehensive
then Alt. #3)
x Requires supplemental funding
from other sources
Issues:x Provides 1&1/3 increase library
space - distinct areas for children,
young adults, adults x Supported by Foundation
x Meets all original Library project
goals
x Likely last major expansion at this
site
x Cost – even with the NEH Grant
and other funds raised the
community would pay a significant
majority of the project costs x Would be most operationally
efficient – would have storage
space on-site
x Most potential effect on
neighborhood (scale, off-site
impacts)
x Can accommodate both current
and future collections.
x Requires supplemental funding
from other sources
Description: Is there another alternative that we
should consider? Use this space or
separate sheet to tell us about it.
Original Library Expansion Project
Goals
The Library Expansion project will:
x Improve library service by providing
new dedicated spaces for library
activities such as reading areas,
reference assistance, and program
spacesx Improve library service by providing
new dedicated spaces for library
collections x Improve library service by providing
functional and efficient staff spaces x Bring the library structures into
conformance with current building and life safety codes and
accessibility requirements
x Restore the existing Carnegie library
to create a beautiful new reading
room
Other Costs
Other costs include the following: architect/engineering; FFE (furnishings, fixtures, & equipment); sales tax; project management; admin overhead; building permits; construction tech support; project contingency. 31 March 2013