HomeMy WebLinkAbout97-079RESOLUTION #97- A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF PORT TOWNSEND AUTHORIZING THE MAYOR TO SIGN CHANGE ORDER #11 FOR $82,189.00 TO THE UNION WHARF RECONSTRUCTION PROJECT CONTRACT WITH HURLEN CONSTRUCTION. WHEREAS, Change Orders are a necessary and common occurrence on large construction projects such as Union Wharf; and WHEREAS, Change Orders are actual changes to the original contract, requiring fair negotiation and agreement by the City and the Contractor, Hurlen Construction Company; and WHEREAS, The additional work was approved by the Union Wharf Advisory Committee and the money is in the budget for the additional work, N O W T H E R E F O R E Be It Resolved that the City Council of the City of Port Townsend authorizes the Mayor to sign Change Order/ti 1 for $82,189.00 to the Union Wharf Reconstruction Project contract with Hurlen Construction Company. ADOPTED by the City Council of the City of Port Townsend, and signed by the Mayor this 7th day of July, 1997. Ju~d)~cCulloch, Mayor ATTEST: AP~P~ Pamela Kolacy, 14Vlcl~Jlahan, City Attorney CM:C:\COUNCILLRESOLUT~ARKS\UWCO 11 .WPD Department of Public Works 5210 KUHN STREET PORT TOWNSEND, WASHINGTON 98368 2061385-7212 206/385-7675 FAX Controct Modification No.: Work Chor'~e Directive No.(s) [ [ Owner:. ~_,,t-r'.,( O~- l~c~'r TowH~m,,kt~, Project Name: L,tl,,tLO~ \~/H.,~'z~ i~,~'c~4~q=~c:no~ Contractor:. ["~~ C~ ~'~.J~o'r~ I1 Project NO.:, The following modifications to the Contract ore hereby ordered: (Use additional pages If required) Contract Amount (~~ont~act Modifications RevVed Contract Amount Contract Tlme (Calculate Days) -3~leduCCX~t~act Modification ct) ' neduttact Moolflcaflon ct) Revised Conl~act Time 1he I~dsecl Contract Completion Date qB By: ~--r/~r,-c~c/ I , UNION WHARF RECONSTRUCTION CHANGE ORDER#II 1 Labor Adjustment 2 Electrical Service and Shelter Lighting 3 RFP #7 Waterline replacement 4 RFP #9 Replace rotten wood sidewalk 5 Sidewalk additional angle iron per engineer 6 Power pole work 7 Taylor street pave 8 A. C. Removal and Base replacement 9 Concrete Planter and Light Pole Base 10 Floating Ramp Gate 1 I Shelter Col. bases 12 H.C.C. extended overhead 13 Bird Electric --Power hook up CREDIT 14 Plate Modification to Ramp Connection TOTAL 6/15/97 $7,880.00 $8,900.00 $21,272.00 $2,092.00 $2,680.00 $960.00 $10,350.00 $6,100.00 $7,400.00 $575.00 $2,900.00 $10,000.00 -$600.00 $1,680.00 $82,189.00 Department of Public Works 5210 KUHN STREET PORT TOWNSEND, .WASHINGTON 98368 2061385-7212 2061385-7675 FAX Ii Date: Contract Modification No.: Work Change Directive No.(s) Project Name: Controcto~ [-~~ I1 Project No.:, The following modifications to the Contract are hereby ordered: (Use additional pages If required) Contract Amount (~~su%n~acr MocSnca.om s Reviled Contract Amount $ Contract Time (Calculate Days) 9B 'o~ · 19 ~'7 Enqine,er Rec?rn. men,clatlon q7-7~ UNION WHARF RECONSTRUCTION CHANGE ORDER #11 1 Labor Adjustment 2 Electrical Service and Shelter Lighting 3 RFP #7 Waterline replacement 4 RFP #9 Replace rotten wood sidewalk 5 Sidewalk additional angle iron per engineer 6 Power pole work 7 Taylor street pave 8 A. C. Removal and Base replacement 9 Concrete Planter and Light Pole Base 10 Floating Ramp Gate 11 Shelter Col. bases 12 H.C.C. extended overhead 13 Bird Electric --Power hook up CREDIT 14 Plate Modification to Ramp Connection TOTAL 6/15/97 $7,880.00 $8,900.OO $21,272.00 $2,O92.00 $2,680.00 $960.00 $10,350.00 $6,100.00 $7,400.00 $575.00 $2,9OO.00 $10,000.00 -$600.O0 $1,680.00 $82,189.00