SR20 PEDESTRIAN WALKWAY
LOGAN ST.TO HANCOCK ST.
City of Port Townsend
City of Port Townsend
Completing the gap
The project is necessary for pedestrians as SR20
crosses a deep ravine at this location
Completing the gap in existing sidewalk in the City’s
upper commercial business district
Pedestrians currently have to walk on private
property so they can stay out of the bicycle lane
Currently
pedestrians
must walk in
the bicycle
lane to
negotiate the
ravine
Once again trying to complete the gap in sidewalk
Option –Elevated Sidewalk
Option -Boardwalk
Examples
Project Costs Project Funding
Phase
Preliminary
Engineering
(Design)
$180,000
Construction $840,000
Other Costs –
Const. Admin.
$180,000
Total Project
Costs
$1,200,000
Funds
Total Funds in
Hand
$120,000
TAP Funds
Request
$190,000
Funds still
needed
$890,000
Total Project
Costs
$1,200,000
Costs & Funding
Program Grant Criteria
Grant Criteria 1
The City of Port Townsend will have project funds
obligated by June 30th of the allocation year.
Grant Criteria 2
The project will be located within the public right of
way and will be open for public access.
Program Grant Criteria Cont’d
Grant Criteria 3
This project meets the following local and Peninsula
RTPO Regional Transportation Plan policies:
Improves pedestrian access on an important regional corridor
(SR20)
Improves regional transportation linkages for pedestrians
Improves safety of existing infrastructure
Improves the regional economy
Program Grant Criteria Cont’d
Grant Criteria 4
The City of Port Townsend is currently working on the WSDOT Prospectus
and Environmental Classification Summary (ECS) which will start the
City’s NEPA review with WSDOT. A Port Townsend Critical Area Permit
and SEPA review will follow. Planned construction in 2018 allows for full
completion of NEPA and other permitting processes and agency approvals.
Grant Criteria 5
At this time only the design is funded.
Grant Criteria 6
The City will secure and provide the minimum match of 13.5% as it seeks
the additional funds to construct the project. A completed design will allow
the City to better apply for other construction funds.