HomeMy WebLinkAbout05.1 Special ProvisionsWSDOT 2018 Standard Specification shall be followed for removal and installation of the permanent marking. Also incorporated into the Contract Documents by reference are:
Manual on Uniform Traffic Control Devices for Streets and Highways, currently adopted edition, with Washington State Modifications, if any.
Standard Plans for Road, Bridge and Municipal Construction, WSDOT/APWA, current edition
City of Port Townsend Engineering Design Standards
DIVISION 1
GENERAL REQUIREMENTS
Description of Work
(March 13, 1995)
This contract is for the Work of approximately 212,569 linear feet of white edge line (4 inch and some 6 inch) and 94,266 linear feet of yellow center line and shall include all labor,
equipment, paint and glass beads necessary to restripe the City streets. The paint shall be Ennis Traffic Paint (Low VOC solvent-based paint) and there are areas of skip line painting
and continuous line painting throughout the city. The City will furnish one person to ride in the striping truck to insure completion and accuracy of the City-wide striping. The Work
shall be completed no earlier than August or later then the end of September, as weather permits. The preferred timeframe is around the middle to third week of August. The Work shall
also include the placement and pickup of protective cones, and any other work, all in accordance with the attached Contract Plans, these Contract Provisions, and the Standard Specifications.
DIVISION 8
MISCELLANEOUS CONSTRUCTION
8-22 Pavement Marking
Section 8-22.3(3)D Line Applications is supplemented with the following:
Pavement markings shall be retro reflectorized. Equipment shall be capable of painting a reasonably clean-edged Stripe, ± ¼ inches, and shall have a bead dispenser directly behind, synchronized
with the paint applicator. The stripe shall be protected until dry. Paint and beads shall be applied within the following limits:
Application Rate or Coverage Per Gallon of Paint:
Minimum Maximum
Paint: 100 sq. ft. 110 sq. ft.
Beads: 7 lbs. 8 lbs.
Section 8-22.4 Measurement is supplemented with the following:
(******)
The measurement for the “Pavement Marking will include mobilization, labor, traffic control, glass beads, paint and freight charges as specified including any applicable taxes to complete
all striping included in this work.
Section 8-22.5 Payment is supplemented with the following:
(******)
“Pavement Marking”, per lump sum