Old Business
A. HPC18-009, City of Port Townsend Old Business, Item A. The sub-committee met with staff including Public Works
Jefferson Street sidewalk– Review of engineer Laura Parsons to review the 3 additional bulb-out locations being
revisions to including Washington Street installed as shown on the conceptual designs presented.
bulb-outs at Adams St. (south side) and
Harrison St. (north side) No public comment during the sub-committee meeting was received.
After review of the materials, concept designs and relevant guidelines, the HPC
sub-committee recommended unanimous approval (2-0) of:
Both the Adams Street bulb-outs as conceptually shown, subject to further design
refinements by staff; and,
The Washington/Harrison bulb-out as conceptually shown, subject to further
design refinements by staff and with a strong recommendation to modify the
striped parking on the south side of Washington to enhance crossing safety.
Additionally, capital improvements to the south side Washington receiving
sidewalk should be included as a bid alternate in the project.
B. HPC18-015, Jefferson County PUD– Above Old Business, Item B. The sub-committee met with staff, who presented the 3
ground utility placement – Revisions for locations sought by WAVE for above ground equipment cabinets (i.e. in the Back
added transformer locations and Alley; in Adams St. along the “Buggy Trail” north of Washington St.; and, the
equipment by other utilities (WAVE & camouflaged “rock” cabinet in the rain garden at the NE corner of Filmore St. and
Century Link) Water St. The sub-committee also reviewed placement of a 3-phase transformer in
the (currently) open landscaping bed in the parking lot behind City Hall.
Topic Motions/Recommendation/Action
After review of the materials and relevant guidelines, the HPC sub-committee
recommended unanimous approval (2-0) of all 4 above-ground utility installations
as presented.
The sub-committee then heard via conference call from Century Link
representative Phil Stevens about their plans for relocating services to various
downtown buildings. The discussion and review of 60% plans was for information
purposes only at this stage; no sub-committee recommendation was sought by
staff at this time as plans for how the relocated services might occur were still
under development.
The sub-committee did recommend unanimously (2-0) that the full HPC be asked
at the next meeting to reconfirm the sub-committee is authorized to continue their
review & recommendation role on any remaining, or revised, utility
undergrounding work associated with this application.