STRATUM GROUP
P.O. Box 2546
Bellingham, WA 98227
January 16, 2018
Brandon Maxwell and Samantha Harper
City of Port Townsend- Public Works Department
250 Madison Street
Port Townsend, WA 98368
Re: Geology Hazard Assessment
Jefferson Street – Taylor Street to Washington Street TIB Project No. P-W-151(P07)-1
Dear Mr. Maxwell and Ms. Harper:
This geologic hazard assessment was conducted to assess the potential risk of landslide and
erosion hazards for the proposed Jefferson Street - Taylor to Washington Street Transportation
Investment Board (TIB) project. It is our understanding that the City of Port Townsend Public
Works Department is planning on constructing sidewalks along the southeast side of Jefferson
Street and the southwest side of Quincy Street. The project will also include widening the paved
street area to accommodate public street parking as well as removing the existing cement lined
stormwater drainage ditch along the southeast side of Jefferson Street.
It is our understanding that the proposed improvements will not be located on the steep slope that
meets the Port Townsend Municipal Code (PTMC) criteria as a geologically hazardous area.
However, because the proposed project will be located within 50 feet of a steep inland bluff
slope, a geotechnical report is required per PTMC 19.05.100.
The scope of our work included an inspection of the project site and vicinity including the inland
bluff slopes, observations of soil and geology units via hand dug test pits on and at the top of the
steep slope and at nearby exposures, review of draft plans and conceptual designs for the project,
review of available geologic maps, historic aerial photographs and historic maps, and review of
lidar (light detecting and ranging) derived imagery. Past observations at similar sites including
areas in the vicinity of the subject property aided in our interpretations. After our initial geology
assessment, we met on site with Public Works staff familiar with the project to discuss the
proposed project and the proximity of the proposed project to the top edge of the slope.
Based on our geology hazard assessment, it is our opinion that the proposed project will not be at
risk of landslide or erosion hazards as long as the recommendations made in this report are
followed. Furthermore, the proposed project will not increase the risk of landslides or erosion on
or off the site as long as the recommendations of this report are followed.
Stratum Group File: 1.1.181.18
2
January 16, 2018
Jefferson Street – Taylor Street to Washington Street TIB Project No. P-W-151(P07)-1
Geologic Hazard Assessment
GENERAL GEOLOGY
The Geologic Map of the Port Townsend South and Part of the Port Townsend North 7.5-minute
Quadrangles, Jefferson County, Washington (Schasse and Slaughter, 2005) indicates that there
are three geologic units located in the vicinity of the project: Vashon recessional outwash sand,
Vashon lodgement till, and fill (Figure 1). Vashon recessional outwash sand is unconsolidated
stratified sand with pebbles and silt. In the Port Townsend area, Vashon recessional outwash
typically forms a thin veneer over thicker deposits of till. The outwash was deposited during the
late stages of the last glacial period approximately 14,000 years ago as the glacial ice melted out
of the area. It has been our experience that this unit is in places poorly sorted and appears to have
been in part derived from ice contact and ice wasting. Vashon lodgment till is a compact and
dense diamicton consisting of very poorly sorted mix of clay, silt, sand, gravel, cobbles, and
scattered boulders. The till was deposited directly by glacial ice when the area was covered by
glacial ice between 18,000 and 14,000 years ago. The fill consists of a mix of sediments, organic
material, rip-rap, and debris emplaced to reshape topography.
Figure 1. Lidar imagery (Jefferson County, 2012) with geology (Schasse and Slaughter, 2005) overlay for the
Jefferson Street Sidewalks Project site. Our site observations differ from the mapped geologic units and contacts.
Stratum Group File: 1.1.181.18
3
January 16, 2018
Jefferson Street – Taylor Street to Washington Street TIB Project No. P-W-151(P07)-1
Geologic Hazard Assessment
While the geologic units mapped by Schasse and Slaughter (2005) are present in the near
vicinity, our site observations are not consistent with the above described mapping. This
discrepancy is primarily due to the scale of the mapping. We hand dug multiple test pits on the
site including the steep slope and observed moderately compact fine sand with gravel and
scattered cobbles (SW) to fine sand with trace silt (SP) (Figures 2, 3). The unit is consistent with
Vashon advance outwash. The deposit is moderately cohesive and well drained, owing to its
limited silt and clay content. The advance outwash was deposited by meltwater streams as glacial
ice advanced towards the area approximately 20,000 to 18,000 years ago. The unit is compact
due to the mass of glacial ice that overrode the area after deposition.
Figure 2. Photograph of fine sand excavated from a hand dug test pit on the steep slope.
Figure 3. Photograph of pebbles within the fine sand unit from a hand dug test pit on the steep slope.
Stratum Group File: 1.1.181.18
4
January 16, 2018
Jefferson Street – Taylor Street to Washington Street TIB Project No. P-W-151(P07)-1
Geologic Hazard Assessment
We also observed Vashon till at a stratigraphically higher position on the road cut exposure on
the northwest side of Jefferson Street. This observation is consistent with the proposed project
location and steep slope below being underlain by advance outwash rather than recessional
deposits as indicated by Schasse and Slaughter (2005). Some of the material we observed near
the surface of our test pits may be side cast material sourced from when the road cut was
excavated and graded. However, based on the test pit excavations, the slope and the area
immediately above the slope is underlain primarily of undisturbed advance outwash that consists
predominantly of fine sand in a dense condition.
SITE SPECIFIC OBSERVATIONS
The proposed project is located on the southeast side of Jefferson Street and the southwest side
of Quincy Street (Figure 4).
Figure 4. Aerial view of project area indicated with red line (modified Jefferson County GIS map)
The proposed sidewalk project will link a currently existing sidewalk along the south side of
Jefferson Street that terminates at Adams Street with a sidewalk on the north side of Washington
Street at Quincy Street. The project will also widen portions of the road to accommodate parking
and remove an existing concrete lined stormwater ditch along the current outer edge of Jefferson
Street (Figure 5).
Stratum Group File: 1.1.181.18
5
January 16, 2018
Jefferson Street – Taylor Street to Washington Street TIB Project No. P-W-151(P07)-1
Geologic Hazard Assessment
Figure 5. Photograph of Jefferson Street showing the car lane, shoulder, parking area and concrete-lined stormwater
ditch. The steep slope is to the right obscured by ivy and brush.
A portion of the project is located near the top edge of a steep slope that slopes down to the
southeast from Jefferson Street and down to the southwest from Quincy Street. The current
topography in the project area, including the street corridor and steep slope are the result of prior
excavation and grading projects. The street was cut into an existing bluff and graded to
accommodate the road by at least the 1870s (from historic maps of Port Townsend). This is
apparent in lidar imagery (Figures 1 and 6). The slope on the southeast (downhill) side of
Jefferson Street appears to have been somewhat modified from its original slope by excavation
into the lower slope from below.
Project area
Steep slope obscured
by ivy
Concrete lined
drainage ditch to be
removed
Stratum Group File: 1.1.181.18
6
January 16, 2018
Jefferson Street – Taylor Street to Washington Street TIB Project No. P-W-151(P07)-1
Geologic Hazard Assessment
Figure 6. Lidar derived bare-earth image of project area indicated with red line (modified Jefferson County GIS)
The steep slope near the southeast side of Jefferson Street ranges in height between 22 and 38
feet with the highest point near the intersection of Adams Street and the slope height gradually
becoming lower as the road descends to the northeast. The measured slope angles along this
section range from 28 degrees (53 percent) to 40 degrees (84 percent) with an estimated average
slope close to 32 degrees (62 percent). Portions of the slope that exceed 40 percent are greater
than 10 feet and therefore, this slope meets the criteria for a geologically hazardous area per
PTMC 19.05.100.B.5.
The steep slope near the southwest side of Quincy Street has a maximum height of 16 feet and
gradually becomes lower as the street descends towards Washington Street (Figure 6). The slope
angles on this slope range from 34 to 45 degrees (67 to 100 percent) with an average of 41
degrees (87 percent). The slope areas that exceed 40 percent also exceed 10 feet in height and
therefore, the portions of this slope above 10 feet in height meet the criteria for a geologically
hazardous area per PTMC 19.05.100.B.5.
As noted in the geology section, soils underlying the steep bluff consist of dense fine sand to
gravely sand that we interpret to be advance glacial outwash. The sand is dense and well drained
and where not obscured by thin colluvium top soil extends to the base of the bluff.
No springs or seeps were observed on the slope. No areas of sliding or mass wasting other than
minor surface soil ravel was observed anywhere on the slopes.
Steep slope area
Stratum Group File: 1.1.181.18
7
January 16, 2018
Jefferson Street – Taylor Street to Washington Street TIB Project No. P-W-151(P07)-1
Geologic Hazard Assessment
Vegetation on the slopes consists of low brush with significant areas covered with English ivy. A
few trees are present on the slope as well including big leaf maple. We noted that the English ivy
is growing on and up several trees and appears to have covered much of the low growing brush
such as rose and snowberry on the slopes. There are several maple trees lining the southwest side
of Quincy Street between the street and the steep slope. Figures 7 and 8 show the slope
vegetation cover.
Figure 7. View of the steep slope below the southeast side of Jefferson Street.
Figure 8. View of the steep slope adjacent to the southwest side of Quincy Street.
Stratum Group File: 1.1.181.18
8
January 16, 2018
Jefferson Street – Taylor Street to Washington Street TIB Project No. P-W-151(P07)-1
Geologic Hazard Assessment
On the Jefferson Street section near the steep slope, the current edge of the travelled car lane
(solid white line) is located between 19 feet and 33 feet from the top edge of the steep slope.
There is a 16-foot long section of road where the top edge is less than 22 feet or less from the
edge of travelled car lane. Along the 90-degree turn from Jefferson Street to Quincy Street, the
edge of the travelled car lane is between 10 and 12 feet from the edge of the steep slope. On the
Quincy Street section, the edge of the travelled car lane is between 10 and 13 feet from the top
edge of the slope. A row of maple trees is located between the edge of Quincy Street and the top
edge of the steep slope.
PORT TOWNSEND GEOLOGICALLY HAZARDOUS AREAS EVALUATION
As per PTMC 19.05.100. B 1 through 6, the following classification criteria were evaluated to
determine if the proposed project location is in a geologically hazardous area. Based on this
evaluation and the conditions described in the above sections as well as our understanding of the
proposed street improvements, the proposed project will not be located within a geologically
hazardous area. However, the proposed project area is located within 50 feet of the top of an
inland geologically hazardous slope (including but not limited to an inland bank of greater than
40 percent that exceeds a vertical height of at least 10 feet) and is therefore within an “inland
bank management zone” and requires a geologic hazard evaluation per PTMC
19.05.100.D.2.f.iii.
19.05.100.B.1: Any area containing soil or soil complexes described or mapped within the
United States Department of Agriculture/Soil Conservation Service Soil Survey for Jefferson
County as having a severe to very severe erosion hazard potential.
Soils underlying the project area are mapped as Townsend gravelly loam 0 to 15 percent slopes.
Townsend gravelly loam is described as being “moderately well drained” by the USDA. These
soils do not have a severe to very severe erosion hazard potential. A small area of the lower slope
near Washington Street is mapped as cut and fill land and described as “somewhat excessively
drained” and not subject to severe to very severe erosion hazards.
Obviously, the steep slope does not match the slope indicated on the soil map as the steep slopes
are up to 100 percent. Furthermore, the description of the Townsend gravelly loam does not
match our site soil observations on the site. The soils map indicates that the parent material is till
and the unit is predominantly gravel. Our soil observations found the soil to be sand and the
parent material to be advance glacial outwash.
The soils we observed are well drained and will not be subject to severe erosion unless
stormwater flows are concentrated on the steep slope.
19.05.100B2: Areas with all three of the following characteristics: a. Slopes greater than 15
percent; b. Hillsides intersection geologic contacts with a relatively permeable sediment
Stratum Group File: 1.1.181.18
9
January 16, 2018
Jefferson Street – Taylor Street to Washington Street TIB Project No. P-W-151(P07)-1
Geologic Hazard Assessment
overlying a relatively impermeable sediment or bedrock; and c. Springs or ground water.
Although the slope below the proposed project area exceeds 15 percent, no geologic contacts or
impermeable boundaries were observed during our site investigation. No perched water or
standing water was observed on or near the slope during our site investigation.
19.05.100B3: Any area potentially subject to mass movement due to a combination of geologic,
topographic, hydrologic factors, but not limited to those areas mapped or described by the Soil
Conservation Service, Washington State Department of Ecology, Department of Natural
Resources or U.S. Geologic Service. The classification may be based on performance standards
rather than mapping.
Based on our inspection of the steep slope, it is our professional opinion that the steep slope is
not at risk of mass movement other than minor surface slope ravel on the steepest slope sections.
The proposed project will not be located on the steep slope and will not be at risk from mass
movement from the steep slope.
19.05.100B4: Any area potentially unstable or subject to erosion or sloughing as a result of
rapid stormwater runoff, soil saturation or undercutting by wave action.
There is no evidence of rapid stormwater runoff or soil saturation on the steep slope. As stated
above, the underlying soil is well drained and compact. As long as stormwater is not directed
onto the steep slope in a concentrated manner, the steep slope will not be subject to erosion
hazards.
19.05.100B5: Any slope of 40 percent or steeper that exceeds a vertical height of 10 feet over a
25-foot horizontal run.
The steep slope to the southeast of Jefferson Street and the steep slope southwest of Quincy
Street have slopes that are greater than 40 percent and exceed a vertical height of 10 feet.
The proposed project will not be located on this steep slope area, but the proposed project will be
located within an “inland bank management zone” per PTMC 19.05.100.D.2.f.iii. because the
proposed project is within 50 feet of the top of an inland geologically hazardous slope (including
but not limited to an inland bank of greater than 40 percent that exceeds a vertical height of at
least 10 feet).
19.05.100B6: Areas subject to severe risk of damage as a result of earthquakes, slope failure,
settlement, soil liquefaction or faulting. These areas are identified by the presence of poorly
drained soils (greater than 50 percent silt and less than 35 percent coarse material) loose sand
or gravel, peat, artificial fill and landslide materials or soils with a high organic content.
Soils within the proposed project are well drained, compact, and are not susceptible to
earthquake induced mass movement, liquefaction, or faulting. Some shallow surface soil
movement may take place on the steep slope during a large seismic event.
Stratum Group File: 1.1.181.18
10
January 16, 2018
Jefferson Street – Taylor Street to Washington Street TIB Project No. P-W-151(P07)-1
Geologic Hazard Assessment
RECOMMENDATIONS
The proposed project will not be located in a geological hazardous area, but will be located
within 50 feet of an identified inland bluff that meets the PTMC criteria as a geologic hazard
area as described in the previous section. This section addresses the relevant applicable
development standards in PTMC 19.05.100.D 2. and 19.100.05.E to the proposed project and
provides specific recommendations for the proposed project near the steep slope along Jefferson
Street and Quincy Street so that the proposed project will not be at risk from landslides or
erosion and the proposed project will not increase the risk of landslides on or off the site.
Buffers and setbacks
Port Townsend CAO 19.05.100 E describes buffers and setbacks requirements for geologically
hazardous areas.
Port Townsend CAO 19.05.100 E 1 states Within the management zones established for marine
bluffs and inland banks under subsections (D)(2)(f)(ii) and (iii) of this section, the buffer width
shall be established by an approved geotechnical report prepared by an engineering geologist
with a Washington specialty license in engineering geology as specified in Chapter 18.220 RCW.
The report shall be based upon the best available science, existing and proposed uses, risks of
slope failure, and coastal erosion rates, if applicable.
Dan McShane is a licensed engineering geologist in the State of Washington and this report is
based on the use of the best available science, the interpretation of slope and geologic conditions
and the expected impacts of construction and the proposed use.
Based on our assessment of the steep slope, it is our opinion that the proposed project will not be
subject to landslides or rapid erosion. Some shallow slope ravel may be expected on the steepest
portions of the slope. Therefore, it is our professional opinion that no buffer or setback is needed
between the sidewalk and the top edge of the 40 percent slopes.
Although no setback is required from the slope that meets the geologically hazardous criteria,
two other considerations may result in a setback from the top edge of the slope: 1) Placing the
sidewalk directly adjacent to the edge of the steep slope could cause some differential settlement
along the outer (nearest to the slope) portion of the side walk, and 2) Placing the sidewalk
adjacent to the slope may require a railing to be located along the sidewalk for safety purposes.
In order to address the potential of differential settlement, we recommend that the sidewalk be
set at least 2 feet back from the top edge of the steep slope in order to avoid the potential for
differential settlement of the sidewalk. It is our understanding after walking the project site and
discussing our results that the sidewalk will be located 2 feet back from the top edge of the steep
slope. If the sidewalk is constructed within 2 feet of the edge of the slope, differential settlement
is possible and the project may require grading or a structure to support the outer edge of the
sidewalk.
Stratum Group File: 1.1.181.18
11
January 16, 2018
Jefferson Street – Taylor Street to Washington Street TIB Project No. P-W-151(P07)-1
Geologic Hazard Assessment
Stormwater Control
Currently street run off flows along the side of the two streets. Along Jefferson Street, between
the street and the slope, there is currently a concrete lined stormwater drainage ditch. The project
will add very minimally to the existing impervious area. The proposed project will capture all
stormwater from the street and sidewalk and transmit the stormwater to the City stormwater
system. The result will reduce the amount of water that reaches the slope and will reduce the risk
of stormwater discharging onto the slope in a concentrated manner.
Erosion Control
Soils underlying the proposed project area consists of well drained sand. The project area will
take place in an area that consists gravel, bare compacted soil, a concrete lined stormwater ditch
and grass and some brush consisting mostly of English ivy. No disturbance of the geologically
hazardous slope will take place.
If work takes place during wet weather, stormwater from the street area should be managed to
prevent concentrated discharge onto the steep slopes.
Vegetation
No vegetation removal will take place on the steep slopes. The existing ground along the
proposed project is gravel, a concrete lined ditch, compact bare soils, grass and English ivy with
minimal other vegetation. A row of trees along the edge of Quincy Street are to be left in place.
The project will cover most of the area with pavement. A couple of feet of soil along the edge of
the sidewalk will likely be disturbed and should be planted with grasses or low growing ground
cover. Post project, trimming back English ivy from encroaching on the sidewalk area will not
cause slope stability problems.
Heavy machinery operation:
Heavy machinery should not be operated on the steep slope itself.
Stratum Group File: 1.1.181.18
12
January 16, 2018
Jefferson Street – Taylor Street to Washington Street TIB Project No. P-W-151(P07)-1
Geologic Hazard Assessment
CONCLUSIONS
The proposed sidewalk expansion project is located near the edge of a steep slope that meets the
criteria for a geologically hazardous area per PTMC 19.05. Although the proposed project will
not be located within the area that meets the criteria of a designated geologically hazardous area,
it is located within an “inland bank management zone” due to its close proximity to the critical
area.
Based on our geology hazard assessment, the proposed project will not be at risk from landslides
or erosion and will not increase the risk of landslides or erosion as long as the recommendations
of this report are followed.
Stratum Group appreciates the opportunity to be of service to you. Should you have any
questions regarding our assessment please contact our office at (360) 714-9409.
Sincerely yours,
Stratum Group
Dan McShane, L.E.G., M.Sc. Geoff Malick, G.I.T., M.Sc.
Licensed Engineering Geologist Geologist-in-Training