SECTION 012300 - ALTERNATES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for alternates.
1.3 DEFINITIONS
A. Alternate: An amount proposed by bidders and stated on the Bid Form for certain work defined
in the bidding requirements that may be added to or deducted from the base bid amount if
Owner decides to accept a corresponding change either in the amount of construction to be
completed or in the products, materials, equipment, systems, or installation methods described
in the Contract Documents.
1. Alternates described in this Section are part of the Work only if enumerated in the
Agreement.
2. The cost or credit for each alternate is the net addition to or deduction from the Contract
Sum to incorporate alternate into the Work. No other adjustments are made to the
Contract Sum.
1.4 PROCEDURES
A. Coordination: Revise or adjust affected adjacent work as necessary to completely integrate work
of the alternate into Project.
1. Include as part of each alternate, miscellaneous devices, accessory objects, and similar
items incidental to or required for a complete installation whether or not indicated as part
of alternate.
B. Notification: Immediately following award of the Contract, notify each party involved, in
writing, of the status of each alternate. Indicate if alternates have been accepted, rejected, or
deferred for later consideration. Include a complete description of negotiated revisions to
alternates.
C. Execute accepted alternates under the same conditions as other work of the Contract.
D. Schedule: A schedule of alternates is included at the end of this Section. Specification Sections
referenced in schedule contain requirements for materials necessary to achieve the work
described under each alternate.
City of Port Townsend SECTION 012300
Mountain View Commons Improvements Alternates
012300 Page 2 of 2
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 SCHEDULE OF ALTERNATES
A. Alternate No. 1.
1. Alternate #1 work include exterior painting of buidings A, B, and C as indicated on the
drawings, with the exception of painting of the canopy where existing canopy is removed
and exterior railings for ramp and stairway at Building A entry.
B. Alternate No. 2
1. Alternate #2 work includes demolition and installation of new fire alarm system for
buildings A, B, anc C as indicated on the drawings.
C. Alternate No. 3
1. Alternate #3 work includes the remodel of Police offices for Rm #506 Unisex Locker
Room, Rm #507 Prosecuting Attny, Rm #508 Legal Asst, Rm #509 Unisex
Shower/Restrm, Rm #510 Staff Restroom
END OF SECTION 012300