HomeMy WebLinkAboutHolcomb; Alley between 29th & 30th Sewer Main ExtensionExisting Discharge
to Storm DitchExisting
Storm Grates
Existing Fire Hydrant
1,500 gpm
Existing Fire Hydrant
1,500 gpm
SS
Existing 8-inch PVC
Gravity SS MainLandis Lane
W
Existing 6-inch
PVC Water Main
Survey Stake
Survey Stake
Pre-Existing SS
Maintenance Hole
Sheet 1 of 1
Sanitary Sewer As-Built Record Drawing
SDP17-029 Sparrowhawk (McDowell)
Hastings Third Addition Block 20 Lots 1 – 10
Between Holcomb St & Gise St
Between 29th St & 30th St
Port Townsend, WA 98368
Jefferson County Parcel 957902001
Original Scale: 1 inch = 20 Ft
26'
2.5'
6" Single Sewer Service with Toning Wire
(Typical of Eight) Marked with 2-inch PVC Pipe Stake
New SS Maintenance Hole
with 45º Channeled Elbow
Invert: 7.26 ft below rim
Compiled by: Everett A. Sorensen, P.E.
Streamline Environmental, Inc.
715 Grant Street; Port Townsend, WA 98368-2405
everett@streamlineenv.com 360-821-9960
October 27, 2017
New SS Maintenance Hole
with 45º Channeled Elbow
Invert: 7.17 ft below rim
Newly-Installed Gravity Main Sanitary Sewer
8-inch PVC ASTM D3034 with Typical Invert Depth 6.5 to 7 ft
Equipped with Eight Side Service Stubs
Newly-Installed Sanitary Sewer 8-inch PVC Vertical Stub-Up with Gasketed Cap
Awaiting Final Grading Prior to Completing with Cast Iron Ring and Lid
8.0'
0 80 12040 160 Ft20