HomeMy WebLinkAbout9307-18C 2 T Y O F PORT TO WN S END
~~
_,~ , .,
BUILDER`S PERMIT ~ INSPECTION RECORD
(See Instructions on Attached Sheet)
THIS CARD MUST HE POSTED AT CONSTRUCTION SITE
CALL 385-2294 fiOR INSPECTION
Permit Number 9307-18 Issued 8/3/93 Treas. No.
Jah Address 929 Madison Zoning R-1 Type N A Occtnanct M-1
Nature of fork Foundation far garage Ose of Buiidingjsj Gara4e
Omer Larry Aase Contractor same as owner
tNESi ENERGY CODE*
1. GEODNDf+ORR: Plumbing
Inspector Date
Z. FCOTINGS;SLA&S: Se*~acks_ iorrs_ Reinforcexnt_ Slab_
j
Inspector d. Date
3. r'OONDATION HALL: Foras_ Reinforcexnt_ Reather Proofing-
- Vents- Crayl Aces ~ ~V Iyspector ~ Date ~' r ~~
4. FLOOR FRAMING:: Girders- Joists- Bridginp_ Shield Dnder Posts- Positive Past/Girder Connect
Girder/Con¢ete-1/2"_ Treated Toad to Concete_ Anchor Bolts t/4iashers_
Inspector Date
5. PLDMBIHG: Drains- Vents- Trans, Clean-outs- Rater Supply- Gas Suop1Y_
Inspector Date
6. MECSABICdL: Furnace- Exhaust` Heat Duc`s_ Inspector Date
i. FBAIQHG: Aalis_ Ceiling Roof Vents Nindovs- ,Air Seal
Ip Stall Peaetratioas_ Chimney Straps- Inspector late
8. INSULATION: Floor _ Rall _ Ceilina_ Baifles_
9. DRYWALL MAILING: Nalls_ Ceiling,
10. DRAINAGE:
Inspector Date
Inspector Date
11. FINAL INSPECTION: Building Plumb. Mech/heating Smoke Det. House No.
• Inspector Date
C a 1 1 4 8 hours before you d i g
for ut i 1 i ty 1 i n e locate s
1- 8 0 0- 4 Z 4- 5 5 5 5
li :''.~ ~'n,i- CSTY OF PORT TOWNSEND i ~~~
ll ~ .J'`~" ~ !, s~t
.~ BUILDER'S PERMIT & INSPECTION RECORD r~ ~ r'
~~
(See Instructions on Attached Sheet) ~~; 1,,n1~~ -
I
• THIS CARD MUST BE POSTED AT CO1~(STRUCTION SITE C~%~J
CALL 385-2294 FOR INSPECTION
Permit Number 9307-18A Issued 9/3/93 Treas. No.
Job Address 929 Madison Zoning R-1 Type 5-N Occupancy R-3 M-1
Nature of cork New residentia garage Ose of Buiidinq(s~ garage
D•,mer Larry & Jacquel i ne AAS Contractor same as owner
;NEW ENERGY CODE*
1. GROUNDWORK: Plumbino
Insaeror Date
2. FQOTLYGS/SLABS: Se*~acks_ corms- Reinforcexat_ SiaD_
3. FOUNDATION WALL: corms
Vents
Inspector Date
Reiniorcexnt_ Weather Proofing-
Crar~1 Acess~ insaector Data
4. FLOOR FRANING~ Girders- Joists- Bridging Shield Dnder Posts- positive Past/Girder Connect-
. Girder/Coacrete-1J2"_ Treated Mood to Con¢ete, ,~chor Bolts r/Washers-
Inspector Date
5. PLDNBING: Drains- Vents- Trans` Clean-outs- Water Suoply_ Gas Suoply_
Inspector Date
6. NECBAHICIL: Furnace- Ezbaust_ Heat Ducts- Inspector Date
i. FRA}IDtG: Walls- Ceiling- Roof Vents ~iindovs= Air Seal`
In Wall Peaetrations_ Chimney Straps- Inspector
8. INSULATION: floor _ Wail _ Ceilinq_ Baffles-
4. DRYWALL NAILING: Walls- Ceiling_
Date
lo. DRAINAGE: required; approved plan attached Inspector Date
FINAL INSPECTION: Building- Plumb. Mech/heating Smoke Det. House No.
Inspector Date
C a 1 1 4 8 hours before you d i g
for u-ti 1 i-ty 1 ins 1oca~tas
1- 8 0 0- 4 2 4- 5 5 5 5
Date
Insaector Date