Permit Number: BLDOZ-248 Issued: 10/30102. Parcel Number: 956500004
Job Address: 301 43rd Street Zoning: R~II Type: VV=N Total Occupant Load: 4
Occupancy: R-3 Nature of Work: Construct Single family residence
Owner: Bishou Brothers Construction Contractor: Same as Owner
•
GENERAL CONDITIONS APPLY -SEE LAST PAGE
SEPARATE PERMITS REQUIRED:
Electrical -Contact Labor & Industries @ 360-417-2702
Street and Utility Development Permit
REQUIRED INSPECTIONS APPROVED/DATE
TEMP EROSION & SDM'T CONTROL
See General Condition No. 1 & attached erosion control details
Silt Fence as needed
Drive Off Mat to restrict sediment from leaving
the site
SLAB/GROUNDWORK PLUMBING ~ - ~h _ ~~~pr, r ~'~ct/
~ ~
Hydronic Tubing
Interior Footing,{or ABWP holdowns /
~u S~er:~ ~ l Z' 6 3 ~O ~ C- ~-
Pressure Test ~ ~,~,~-
Pipe Joints Exposed
Pipe Bedding
Trap Seal Protection (if applicable}
FOOTINGS J ~ 3 (2 S(u .~
Setbacks
F
tin
s C
~
g
oo ~ ,
1,
Forms
Reinforcement
LIFER ~ I ~c~''
~l<i . vr4 ., U i n,
/ ~ ~ --~C~-I' ;
• Call 48 hours before you dig for utility line locates
1-800-424-5555
Page 1 of 4
Pwmit#BLD02-216 ~
t
REQUIRED INSPECTIONS
APPR(lVF'll/nATF.
FOUNDATION S-~,d~, w ~~ ~~:, V5
Stem Wall ~ob
-1 aUon
Forms ---~--
Reinforcement
Anchor Bolts & Washers -
ABWP Holdowns
Waterproofing
PLUMBING: +~~ b~ .~ ~~, Io.~
i~
Rough-In (D-V-T & Clean outs)
Gas Supply
Water Supply
Water Ilammer Arrestor Q clothes and dishwasher
Hose Bibs (backflow protection required)
Pipe Insulation (R-3)
Pressure Reduction Valve if> 80 psi
Water HeaterBoiler
Seismic Restraint
Pressure relief valve drain to exterior, terminate 6" - 24" above ground
MECHANICAL
Boiler -installation instructions shall be on-site at time of i»spection
Whole House Fan - Qa master bath
Source Specific Fans
Environmenta r x aus uctmg w backdraft dampers), insulation
(R-4) and terminus (located 3' from openings)
FRAMING
Walls
Treated Wood to Concr~e
Positive Connections
Anchor Bolts & Washers
Ceiling/Roof
Rafter Positive Connection
Blocking
E~ 2
~ '
~ ~
Roof Venting - @ eave & gable C
/
Windows -escape
Windows U-factor - .40 or better
NFRC window sticker must be on windows and doors
Air Seal
Fresh Air Intake (Window Ports)
Doors U-factor - .20 or better
Fire Blocking
Weather Resistive Barrier
Ca1148 hours before you dig for utility line locates
I-800-424-5555
Page 2 of 4
1 RF.nTTTRFII TNCPF.CTinNS
ramie x stDO2-zae
APPROVED/DATE
INSULATION
Slab R-10 under entire slab)
;~,(,~~ o~~g SlZ~lo3
Walls-(Rl21)
tieilin - (R=38 )
Baffles `~ ~ 7-
a er: pam
DRY WALL NAILING
Walls
(~,~ ~~ ~Z~p3
Ceiling , l~~
FINAL
Public Works ign-Off
LPG ~~ 8~z~a3
House Numbers - 5"minimum /~,,_
r
Plumbing C~ ~
~
J{/'1f~~ 7"/
Jp ~
~~,%
Mechanical/Heating ~
l
Insulation Certificate
Vapor Barrier Paint Certificate
Smoke Detectors
Final -Building
• (TF,NERA , CONDITTONS
1. Contractors working on this project are required to Gave a Labor & Industries contractor's registration
number and a City business license. Failure to provide proof of this documentation prior to work may
result in job shut down while this is accomplished.
2. Temporary erosion and sediment control (TTsSC) measures shall be installed on-site and inspected prior
to beginning construction; call 385-2294. Measures shall include installation of silt fencing and graveled
construction entrance (see attached details). Adjacent rights-of--way shall be kept free of dirt debris. Soils
exposed during construction shall be temporarily stabilized with mulching, plastic sheeting, eta Soils
shall be permanently stabilized with seeding, plantings, sodding, etc, once construction is completes
Applicant is responsible for protection of adjacent properties.
3. All elements of engineering including nailing, holdowns, sheathing, and alternate braced wall panels
(ABWP) require inspection prior to cover.
4. Owner or owner's agent shall review and oversee correction of any and all deficiencies noted by required
inspections.
5. Re-inspection is required after inspection report corrections are completed.
6. The Building Department is unable to pass final inspection on your project until Public Works
requirements have been completed and inspected. For Public Works inspection ca11385-2294. A
schedu{ing the Building Department's final inspection.
Ca1148 hours before you dig for utility line locates
1-800-424-5555
Page 3 of 4
~,.~.~ ~
7. Final Inspections are required prior to occupancy; A Certificate of Occupancy is required fora non-
residential project.
8. All building permits ezpire if no progress has been made within sia months, or if no inspections are done
by the Building Department within ooe year. Call for at least one inspection per year to keep your
building permit active.
9. Revisions require submittal and approval rior to making changes in the f-eld. Contact the Building
Department (379-3208) prior to making changes to the approved plans.
10. POST THIS PERMIT ONSITE WITH THE APPROVED PLANS.
Ca1148 hours before you dig for utility line locates
1-800.424-5555
Page 4 of 4