Permit Number: BLDOI-241R-1 Issued: 03/11102 Parcel Number: 947-600-104
Job Address: 4250 Wilson Street Zoning: RR=I Type: VV=N Occupancy: U_1
Total Occupant Load: N C Nature of Work: Rev #1: Add caroort to Qaragelsin¢le family residence.
Owner: Ed Underwood
Contractor• Owner
GENERAL CONDITIONS APPLY -SEE LAST PAGE
SEPARATE PERMITS REOUIItED:
Electrical -Contact Labor & Industries @ 360-417-2702
REQUIRED INSPECTIONS
APPROVED/DATE
FOOTINGS
Setbacks ~/2
Forms
Reinforcement
Pier Footings - 24" x 24" x 24"
FRAMING:
Nailing for Ledger & Sheathing
~
Walls Z/
Beam
Rafters
Roof
Blocking
Positive Connection post-to-footing
Positive Connection post-to-beam
Rafter Positive Connection
Weather Resistive Barrier
Ca- 4S boors before you dig for utility line locates
I-800-424-5555
Page 1 of 2
s~aa~mmrtaswo~-znixa
FINAL
Smoke Detectors throughout existing construction per
1997 UBC; battery powered okay
House Numbers - 5" high
Final -Building ~l/l 7f
GENERAL CONDITIONS
1. Contractors working on this project are required to have a Labor 8c Industries so~ractor's
re¢istration number and a City business license. Failure to provide proof of this documentation prior to
work may result in job shut down while this is accomplished.
2. Temporary erosion and sediment control (TESC) measures shall be installed on-site and inspected
prior to beginning construction; ca11385-2294. Measures shall include installation of silt. fencing and
graveled construction entrance (see attached details). Adjacent rights-of way shall be kept free of dirt
and debris. Soils exposed during construction shall be temporarily stabil¢ed with mulching, plastic
sheeting, etc. Soils shall be permanently stab~7u:ed with seeding, plantings, sodding, etc. once
construction is complete. Applicant is responsible for protection of adjacent properties.
3. AU elements of engineering including nailing, holdowns, sheathing, and alternate braced wall panels
(ABWP) require inspection prior to cover.
4. Owner or owner's agent shall review and oversee correction of any and all deficiencies noted bt~
required inspections.
5. Re-inspection is required after any corrections are completed
6. The Building Department is unable to pass final inspection on your project until Public Works
requirements have been completed and inspected For Public Works inspection ca11385-2294; a
minimum of twenty-four hours notice is required Public Works approval must be received prior to
scheduling the Bu>7ding Department's final inspection.
7. Final Inspections and Certificate of Occupancy are required PRIOR to occupancy.
8. AU building permits expire if no progress has been made within siz months, or if no inspections are
done by the Bm7ding Department within one year. Call for at least one inspection per year to .keep
your building permit active.
9. Revisions require review and approval prior to making changes is the field. Co~etact the Building
Department at 379-5086 prior to making changes to the approved plans.
10. POST THIS PERMIT ON-SITE WITH THE APPROVED PLANS.
Ca1148 hours before yon dig for ut~7ity line locates
i-800-424-5555
Page 2 of 2
Waterman & Keta BWIdMg
181 Quinq Strew, Suite 3B1
Port rewnaeed. WA 98}68
PMne: Jblb379J2B8 Faa }6p385-7675
CITY OF PORT TOWNSEND
CONSTRUCTION PERMIT & INSPECTION RECORD
THIS CARD MUST BE POSTED AT CONSTRUCTION SITE
Call 385-2294 for Inspection
Permit Number: $LDOI-241 Issued: 1114102 Parcel Number: 947-600-104
Job Address: 4250 Wilson Street Zoning: R-I Type: VV=N Occupancy: R-3/U-I
Total Occupant Load: 512 Nature of Work: New Single-family Dwellin¢ w/ eara2e
Owner: Edwin Underwood
Contractor: Hammer Head Custom Homes. Inc.
GENERAL CONDITIONS APPLY -SEE LAST PAGE
SEPARATE PERMITS REQUIRED:
Electrical -Contact Labor & Industries @ 360-417-2702
RF(ITTTRF.TI TNCPF.f'TTCINC
APPRnVF,D/DATE
TEMP EROSION & SEDIMENT CONTROL
See General Condition #2
Silt Fence as needed
Drive Off Mat per attached details
FOOTINGS %~~ ~~ ~6~
Setbacks
Footings
Forms
Reinforcement
Interior Footings
Porch Piers
LIFER
FOUNDATION
Stem Wall
Farms
Reinforcement
Anchor Bolts w/ 2" x 2" x 3/16" square washers
Vents -16 required
Crawl Access
Beam Pockets
Alternate braced wall panel (ABWP) holdowns
@ garage door
Ca1148 hours before you. dig for utility line locates
1-800-424-5555
Page 1 of 4
s
Building Pemd[ #BLDO1-241
REQUIRED INSPECTIONS APPROVED/DATE
SLAB -Non-Structural @ garage
ABWP holdown hardware
FLOOR FRAMING
Engineered BCI plan to be on-site @ time of
inspection
Girders
Joists
~~
Blocking
Shield under Posts ~0 5 G / ~ ~ 0-Z
Positive Connection
Girder to Concrete
Beam Pockets
Treated Wood to Concrete
Anchor Bolts & Washers
PLUMBING:
Rough-In (D-V-T & Clean Outs)
Water Supply
Water Hammer Arrestor @ clothes &
dishwasher
Hose Bibs (backflow protection. required)
Pipe Insulation - R-3
Pressure Reduction Valve if> 80 psi
Water Heater
R-10 under
Seismic Restraint - 2 places
18" A.F.F.
Pressure relief valve drain to exterior
MECHANICAL
Electric Forced Air
Manufacturer's Installation Instructions to be /
f
on-site @ lime of inspection
~
y~~D~
~
l
~~
Ducts & Duct Insulation -Supply/fresh air ~
" `/(
~
~
(
ducts in conditioned space: R-4; heating ducts in (
unconditioned space: R-$
Whole House Ventilation
HVAC Integrated Fresh Air
T' Smooth Duct minimum
Terminal Element - 8"
Clock timer on furnace fan
Other than motorized damper requires letter
of certification for flow rates
See next a e
Ca1148 hours before you dig for utility line locates
1-800-424-5555
Page 2 of 4
u
Building Permit #BLD01.241
RF,OiITRED INSPECTIONS APPROVED/DATE
•
.,
MECHANICAL continued
Source Specific Fans
Environmental Air Exhaust ducting (with
backdraft damper), insulation (R-4) and terminus
(located 3' from opening)
FRAMING
Walls
Alternate Braced Wall Panels ~~~~ ~ ~-
Roof-Engineered mrssplan to be on-site at l.~
time of inspection
Attic Venting -ridge & eave
Ceilings
Posts, beams & headers
Windows -egress
Windows -safety glazing
Windows Ufactor - .40 or better
NFRCwindow sticker must be on
Windows, skylights & doors at inspection time
Air Seal
Skylights - .58 or better
Doors Ufactor - .10 or better
Truss Positive Connection
Fire Blocking
Weather Resistive Barrier
INSULATION
Floor (R-30)
Wall(R-19) l
~v ~Z
Ceiling (R-38 )
Bathes
Vapor Bamer: paint
Crawl space - 6 mil black poly
DRY WALL NAII.ING
Walls
~j// ~~v
Ceiling
Garage/House Occupancy Separation %
Interior Braced Watl Panels
Call 48 hours before you dig for utility line locates
I-800-424-5555
Page 3 of 4
t ,_ ,
suaaing raron #BI.DOt•aai
Public Works Sign-Off
House Number - 5"numbers
Plumbing
Mechanical -Ventilation Certification for
Integrated System
Insulation Certificate
V. B. Paint Certificate
Smoke Detectors
Final -Building ~ ///s JO Z
GENERAL CONDITIONS
1. Contractors working on this project are required to have a Labor & Industries contractor's
reeistration number and a City business license. Failure to provide proof of this documentation prior to
work may result in job shut down while this is accomplished.
2. Temporary erosion and sediment control (TESC) measures shall be installed on-site and inspected
prior to beginning construction; ca11385-2294. Measures shall include installation of silt fencing snd
graveled construction entrance (see attached details). Adjacent rights-of way shall be kept free of dirt
and debris. Soils exposed during construction shall be temporarily stabilized with mulching, plastic
sheeting, etc. Soils shall be permanently stabilized with seeding, plantings, sodding, etc. once
construction is complete. Applicant is responsible for protection of adjacent properties.
3. All elements of engineering including nailing, holdowns, sheathing, and alternate braced wall pan
(ABWP) require inspection prior to cover.
4. Owner or owner's agent shall review and oversee correction of any and all deficiencies noted by
required inspeMions.
S. Re-inspection is required after any corrections are completed.
6. The Building Department is unable to pass final inspection on your project until Public Works
requirements have been completed and inspected. For Public Works inspeMion ca11385-2294; a
minimum of twenty-four hours notice is required. Public Works approval must be received prior to
scheduling the Building Department's final inspection.
7. Final Inspections and Certificate of Occupancy are required PRIOR to occupancy.
8. All building permits ezpire if no progress has been made within siz months, or ii no inspections are
done by the Building Department within one year. Call for at least one inspection per year to keep
your building permit active.
9. Revisions require review and approval prior to making changes in the field. Contact the Building
Department at 379-5086 rior to making changes to the approved plans.
10. POST THIS PERMIT ON-SITE WITH THE APPROVED PLANS.
Call 48 hours before you dig for utility line locates ~`